Latest research: initiation, Nov 23, 2026 · Market value $5.4bn
IRENBuyTarget $17.81+50.7% expected
Our view, Nov 23, 2026
A 20% shot at a $57 bull case outweighs a 35% risk of zero
IREN is a former Bitcoin miner that now rents NVIDIA GPU clusters from its own data centers in Texas and British Columbia. The market prices the credit stress after a 74% fall, but misses the option-like payoff if its asset debt holds.
Where the price could be in 12 months
Circle size shows how likely we think each case is. Case values are 12 months ahead; the target weights all three. Source: Penmark Research.
Our FY28E earnings forecast is $0.94 a share below analysts’
For FY27E we forecast earnings per share of −$2.71, against analysts’ −$3.42. For FY28E we forecast earnings per share of −$1.17, against analysts’ −$0.23.
Our earnings per share forecasts against analysts’
Our estimateAnalysts’ forecast
Earnings per share as the report gives them. Analysts’ forecast is the consensus figure in the report. Source: Penmark Research estimates.
GPU and memory cost inflation to $44m/MW (45% probability) would cut our base DCF value by $8.08 a share, to zero.
A year-six supply glut that resets renewals to $17m/MW (30% probability) would also cut base DCF value by $8.08 a share.
If lenders cap asset debt at $1.5bn, the build stalls at 0.6GW and forces equity at 75% of the price, costing up to $8.08 a share (35% probability).
What bears get right. Management cut FY27 capex by about $7.5bn within ten weeks of Q4 results, missed its December 2025 AI revenue date and still faces about $6bn of unfunded FY27 capital. A credit freeze forcing over $2.5bn of share sales below $11 would push the equity toward zero.
Dates to watch
We expect 300MW live by 28 February. Handing over by 31 January adds $0.23 a share; slipping to end-April costs $0.45.
We expect $262m of revenue, $250m of it from AI, and progress toward $5.0bn of debt on unencumbered assets.
We assume $20.0m/MW. Signing at $22m/MW, as one recent five-year deal did, adds $2.90 a share.
Dell deliveries show the real GPU bill. $36m/MW adds $10.78 a share; $44m/MW wipes out our $8.08 base value.
The funded 0.3GW program lifts operating AI annualized run-rate revenue from $1bn to over $4bn by February 2027, anchoring $3.8bn (49%) of FY28E revenue.
Five-year GPU replacement holds our base DCF value to $8.08, 31.6% below the $11.82 share price.
Our 1.7GW bull case is worth $57.00 today with a 20% probability, against a 35% chance that the equity is worth $0.00.
Penmark Research rates IREN (IREN) Buy, with a 12-month price target of $17.81, +50.7% from the $11.82 share price at our latest report. We expect a return of more than 10% over the next 12 months.
What is the IREN price target?
Our 12-month price target for IREN is $17.81, set in our initiation of Nov 23, 2026. Our bear case values the shares at $0.00 and our bull case at $67.53. The target comes from the probability-weighted value of our bull, base and bear cases.
Will IREN stock go up?
Our IREN stock forecast is a 12-month price target of $17.81, +50.7% from the $11.82 share price at our latest report, which is why we rate it Buy. Our bear case puts the shares at $0.00 (−100.0%) and our bull case at $67.53 (+471.3%). No forecast is certain; the main risks are below.
What does IREN do?
IREN builds and runs data centers and NVIDIA GPU clusters in Texas and British Columbia, renting AI computing capacity to hyperscalers and AI labs.
What are the main risks to IREN stock?
GPU and memory cost inflation to $44m/MW (45% probability) would cut our base DCF value by $8.08 a share, to zero.
A year-six supply glut that resets renewals to $17m/MW (30% probability) would also cut base DCF value by $8.08 a share.
If lenders cap asset debt at $1.5bn, the build stalls at 0.6GW and forces equity at 75% of the price, costing up to $8.08 a share (35% probability).
What is Penmark’s latest research on IREN?
Our latest report is our initiation of Nov 23, 2026, “Initiate at Buy with an $18 target as bull upside outweighs tight base-case GPU returns”. IREN is turning from a Bitcoin miner into an AI cloud provider, and its funded 0.3GW program should lift operating AI annualized run-rate revenue from $1bn to over $4bn by February 2027. Five-year GPU replacement holds our base DCF value to $8.08, below the $11.82 price, but a 20% chance of a $57.00 bull case…