AI cloud revenue grows to $15.3bn by FY29EFY25 to FY29
IREN Limited (NASDAQ: IREN), initiation of coverage, Nov 23, 2026
A 20% shot at a $57 bull case outweighs a 35% risk of zero
IREN is a former Bitcoin miner that now rents NVIDIA GPU clusters from its own data centers in Texas and British Columbia. The market prices the credit stress after a 74% fall, but misses the option-like payoff if its asset debt holds.
- Our rating
- Buy
- 12-month target
- $17.81
- Price, Nov 20, 2026
- $11.82
- Expected return, with dividend
- +50.7%
What IREN is now
IREN has turned its Bitcoin power sites into an AI cloud business
IREN owns substations, liquid-cooled halls and NVIDIA GPU clusters in Texas and British Columbia. Hyperscalers and AI labs such as Microsoft pay fixed monthly fees under three-to-five-year contracts priced per megawatt of computing load.
In Q1 FY27, AI cloud brought in $200m, 88% of sales, while Bitcoin mining faded to $28m before its December exit. Owning the power leaves 86 cents of AI gross profit per dollar of sales, but each megawatt needs about $60m of capital.
Fiscal years end 30 June. Q1 FY27 is the quarter to 30 September 2026. Source: company filings.
Fiscal years end 30 June. FY25 and FY26 reported; FY27 to FY29 are our estimates. Source: company filings, Penmark Research estimates.
What you are really buying
The $12 price sits above our $8 base value but ignores the bull case
Our ten-year cash flow model, at a 12.5% discount rate, puts the base case at $8.08 a share, $3.74 below the $11.82 price. Five-year GPU replacement and $38.5bn still to spend through FY28E hold it down.
The price misses the bull case. Weighting today’s $57.00 bull case and the $0.00 bear case adds $6.96, for $15.04 today. Twelve months of expected return at an 18.5% cost of equity lifts that to our $17.81 target.
Base case value: ten-year discounted cash flow value per share at a 12.5% weighted average cost of capital, today’s values. The weighted step adds $9.78 from the 20% bull case and takes $2.83 for the 35% bear case. Expected return uses an 18.5% cost of equity. Source: Penmark Research estimates.
Where we disagree: the price of renewals
Renewals at $23m per megawatt would more than double our $8 base value
IREN’s substations and halls last 20 years, so the second contract cycle needs only new GPUs: $36m per megawatt instead of $60m. That makes the renewal price, from FY32–33E, the biggest swing in value.
At $11.82 the market implies renewals at $21.7m/MW, just above our $21.0m base. A recent five-year deal signed near $22m/MW, and old H100 clusters re-contracted at twice their first price. Renewals at $23m/MW lift our base value to $18.45.
Renewal price: what customers pay per megawatt of computing load after the first five-year contract. Base value: ten-year discounted cash flow value per share, all else at our base case. Source: Penmark Research estimates.
Where we disagree: funding
Customer prepayments and asset debt can cap new shares at $2.5bn
Short interest reached 94.68m shares by 30 October 2026, as bears bet that IREN’s $18,947m of commitments will force heavy share sales below $12. We think prepayments and asset debt do most of the work.
In our base case customers prepay 35% of GPU costs (recent deals: 45–55%) and IREN borrows $5bn against shells and GPUs it already owns. That leaves $2.5bn of new shares at $11.23. In the bull case, $8bn of asset debt means none.
Funding for 9M FY27E to FY29E. Debt combines new GPU financing, new data-center financing and debt on existing unencumbered assets. Fiscal years end 30 June. Source: company filings, Penmark Research estimates.
Where we disagree: how fast the megawatts arrive
Our FY27E EBITDA sits 42% below analysts’, then matches them in FY28E
The funded 0.3GW program should lift operating AI run-rate revenue from $1bn to over $4bn by February 2027. Analysts assume it starts in early January; we assume end-February, with 95% of contracted revenue collected.
That puts our FY27E adjusted EBITDA, profit before interest, tax, depreciation, amortisation, stock pay and one-offs, at $1,062.2m against analysts’ $1,816.0m. Once the program runs a full year, our FY28E $5,666.9m is 2.7% below theirs.
Adjusted EBITDA: profit before interest, tax, depreciation, amortisation, stock-based pay and one-off items. Fiscal years end 30 June. Analysts’ forecasts are TIKR and MarketScreener consensus, November 2026. Source: company filings, Penmark Research estimates.
The odds
In 12 months the bull case is worth about $68, the bear case nothing
In 12 months we see the bear case at $0.00, the base case at $9.57 and the bull case at $67.53. Weighting them 35%, 45% and 20% gives our $17.81 target, +50.7% from $11.82.
Our conviction is low. A discount rate 1 point higher, IREN’s own five-year beta or the base case alone each cut the expected return below our +10% Buy line. A bull weight below about 12% would also mean a Hold.
- Bull, 20%0.3GW live in January 2027, 1.7GW by FY31, $22–24m/MW pricing, $40m/MW GPUs and $8bn of asset debt with no new shares.
- Base, 45%0.3GW live end-February 2027, 0.8GW by June 2028 and 1.4GW by FY31, $21m/MW renewals and $5bn of asset debt.
- Bear, 35%0.3GW slips to April 2027, the build stalls at 0.6GW, renewals fall to $14m/MW and asset debt is capped at $1.5bn.
Circle size shows how likely we think each case is. Case values are 12 months ahead; the target weights all three. Source: Penmark Research.
What would change our mind
The February handover and 2027 GPU costs will test the call first
Our Buy rests on a 20% chance of the bull case. The numbers that swing value most are what IREN pays for GPUs per megawatt and the price it gets on new deals.
Both show up through 2027. A handover slip past end-April with delay credits, GPU costs heading to $44m/MW, or more than $2.5bn of share sales below $11 would cut our rating.
We expect 300MW live by 28 February. Handing over by 31 January adds $0.23 a share; slipping to end-April costs $0.45.
We expect $262m of revenue, $250m of it from AI, and progress toward $5.0bn of debt on unencumbered assets.
We assume $20.0m/MW. Signing at $22m/MW, as one recent five-year deal did, adds $2.90 a share.
Dell deliveries show the real GPU bill. $36m/MW adds $10.78 a share; $44m/MW wipes out our $8.08 base value.
We expect 597.5MW by December 2027 and the full 800MW by June 2028. Reaching 800MW in December adds $0.90.
Penmark Research. This summary draws on our initiation report on IREN Limited, published Nov 23, 2026. It is not investment advice. Analyst certification, rating definitions and important disclosures are in the full report.