Initiate at Hold, target about $11: $13bn funding bill offsets $41bn lease book
We initiate coverage of Applied Digital (APLD) at Hold with an $11.38 12-month price target, implying 6.9% downside. Applied Digital designs, builds and leases liquid-cooled artificial intelligence (AI) data centers across North Dakota and the southern United States. The share price implies 10.2x FY30E earnings before interest, taxes, depreciation and amortization (EBITDA). Our lease-by-lease discounted cash flow (DCF) value is $7.17 because it uses an 8.74% weighted average cost of capital (WACC) and deducts tax, stock-based pay, lease expiry and refresh costs that a perpetuity multiple leaves out.
- Finite lease cash flows are worth about $7 a share, far below our 13.5x Street-style reference of about $27. Our lease DCF at 8.74% WACC deducts cash taxes from FY33, ongoing stock-based compensation (SBC), 20% non-renewal risk, $2.6bn of refresh capital expenditure (capex) and a 7.5% CoreWeave expected rent loss from FY30.
- A $13bn funding wall hands priority economics to project lenders and Macquarie. Funding contracted campuses pushes debt and Macquarie 12.75% payment-in-kind (PIK) preferred claims to $19.9bn by FY30E, leaving common stockholders subordinate to $1.1bn of FY30E annual interest and $620m of FY30E Macquarie PIK accrual.
- Build-cost inflation, CoreWeave concentration and governance skew risk downward. CoreWeave represents ~26% of contracted rent (we model a 7.5% base rent loss from FY30E), capex at Meta's benchmark ($13.5m/MW) cuts base value to $4.08, and FY26 named executive pay hit $332m (grant-date value, DEF 14A) alongside a $100m related-party credit line to Base Electron ($59.3m drawn).
What the market is missing. The Street’s mean target is $56.67 (17 Buy, 2 Hold, 0 Sell), led by bulls such as Needham applying 19.5x–21x perpetuity multiples to FY29E EBITDA. Our FY28E revenue of $2.65bn (GAAP basis) is 42% above consensus of $1.87bn, yet earnings per share (EPS) stay negative through FY31E because interest and Macquarie’s PIK accrual exceed operating profit.
Catalysts (12-month rating horizon). Ready-for-service (RFS) energizations across 750 megawatts (MW) between December 2026 and October 2027, leasing of Polaris Forge 2's remaining 100 MW by March 2027, and project debt closings on 810 MW of hyperscaler campuses (DF1, PF3 and DF2) in 1H CY27 will test funding costs and capex discipline.
Valuation and why Hold, not Sell. Our bull case ($31.68, 20% weight) supplies $6.34 of our $9.92 weighted value (50% Base at $7.17, 30% Bear at $0); rolling forward 12 months at a 14.66% cost of equity gives an $11.38 target (−6.9%, Hold). Base DCF alone rates Sell; shares rate Buy below $10.34 and Sell above $12.64 (3% away).
Risks. Every robustness test we ran changes the rating. The base case alone rates Sell (−33%), while a one-point lower WACC makes it a Buy (+20%); the Hold rests on the 20% bull weight. Upside risk: our 8.74% WACC relevers the data center REIT asset beta with no debt beta while charging an 8.0% cost of debt. Built consistently, it would be 7.3% to 7.4%, which would put base value above the $12.22 price (the price implies 7.8%). This is the main reason conviction is Low.
| Ticker / Exchange | APLD / NASDAQ |
| Share price (close) | $12.22 |
| 52-week range | $11.49 – $49.65 |
| Market cap (basic / dil.)* | $3.69bn / $3.98bn |
| Enterprise value (model)* | $8.02bn |
| 3M avg daily value | $486.3m |
| Short interest (% float) | 66.5m (24.3%) |
| Dividend yield | 0.0% |
| Fiscal year end | 31 May |
| Street consensus (B/H/S) | $56.67 (17/2/0) |
Source: Databento and Yahoo Finance daily closes to 24 Nov 2026
| Performance (24 Nov 2026) | 1M | 3M | 12M |
|---|---|---|---|
| APLD absolute | −33.0% | −54.6% | −48.6% |
| Rel. to DC REIT (DLR)* | −30.2% | −48.2% | −50.6% |
| Key Financials ($m, May FY) | FY25A | FY26A | FY27E | FY28E | FY29E |
|---|---|---|---|---|---|
| Adjusted revenue (ex ChronoScale) | 144 | 540 | 957 | 2,487 | 3,326 |
| Revenue growth (%) | n.a. | 274.3% | 77.3% | 159.9% | 33.7% |
| Adjusted EBITDA | 20 | 107 | 457 | 1,472 | 2,263 |
| Adjusted EBITDA margin (%) | 13.6% | 19.9% | 47.7% | 59.2% | 68.0% |
| Net income to common | (234) | (249) | (588) | (388) | (324) |
| EPS, core basic ($) | (1.16) | (0.91) | (1.95) | (1.25) | (1.03) |
| EPS growth (%) | n.m. | n.m. | n.m. | n.m. | n.m. |
| Free cash flow (ex prepay) | (797) | (2,776) | (10,168) | (4,082) | 668 |
| Multiples and Ratios (at $12.22) | FY25A | FY26A | FY27E | FY28E | FY29E |
|---|---|---|---|---|---|
| P/E (adjusted EPS) | n.m. | n.m. | n.m. | 17.9x | 11.1x |
| EV / Adjusted EBITDA | 408.4x | 74.7x | 17.5x | 5.4x | 3.5x |
| Price / Book (P/B)† | 7.4x | 2.1x | 2.5x | 3.0x | 3.5x |
| FCF yield (%) | −21.6% | −75.2% | −275.3% | −110.5% | +18.1% |
| Dividend yield (%) | 0.0% | 0.0% | 0.0% | 0.0% | 0.0% |
| Return on equity (ROE) | −47.0% | −14.5% | −39.6% | −31.1% | −31.1% |
| Net debt / Adjusted EBITDA | 33.6x | 32.1x | 22.6x | 9.3x | 5.7x |
| P/E at our target ($11.38, adj.) | n.m. | n.m. | n.m. | 16.7x | 10.3x |
A base value near $7 and a 20% bull weight put our target near $11
Source: Yahoo Finance; Penmark Research estimates (points show 12-month values)
| Case | Prob. | Value ($) | vs Price | Key Drivers |
|---|---|---|---|---|
| Bull | 20% | $31.68 | +159.3% | Capex $11m/MW, +300 MW new lease, 1.5% escalator, 95% renewal |
| Base | 50% | $7.17 | −41.3% | 1.56 GW on time, PF2 +100 MW (80%), 7.5% PF1 loss, $12m/MW, 8.74% WACC |
| Bear | 30% | $0.00 | −100.0% | 6m funding delay, $13.5m/MW capex, PF1 −25% rent, 50% renewal |
| Weighted Value | 100% | $9.92 | −18.8% | Present equity value (24 Nov 2026) |
| 12m Target (Hold) | n.a. | $11.38 | −6.9% | Rolled 12m at 14.66% cost of equity (Ke); 0% div. |
Why Low Conviction: Equity sits behind $11.4bn of FY27E debt and $3.1bn of Macquarie preferred units. Our Hold rests on the 20% bull weight and 8.74% WACC: base case alone ($7.17) already rates Sell (−33% 12-month return), whereas WACC −100bp lifts Base to $12.79 (Buy, +20%) and WACC +100bp cuts Base to $2.47 (−77%).
| Fiscal year ending May | FY25A | FY26A | FY27E | FY28E | FY29E |
|---|---|---|---|---|---|
| Adjusted revenue | 144 | 540 | 957 | 2,487 | 3,326 |
| HPC base rent and recoveries | 0 | 115 | 623 | 2,007 | 3,176 |
| Net operating income (NOI) | 0 | 90 | 462 | 1,471 | 2,314 |
| Adjusted EBITDA | 20 | 107 | 457 | 1,472 | 2,263 |
| D&A and stock-based comp. | (121) | (288) | (358) | (767) | (1,082) |
| Net interest, tax and other* | (130) | (2) | (387) | (644) | (954) |
| Macquarie PIK and pref. div. | (3) | (66) | (300) | (449) | (551) |
| Net income to common | (234) | (249) | (588) | (388) | (324) |
| Fiscal year ending May | FY25A | FY26A | FY27E† | FY28E | FY29E |
|---|---|---|---|---|---|
| Consolidated net income | (231) | (184) | (288) | 62 | 227 |
| D&A, SBC and non-cash | 116 | 274 | 513 | 767 | 1,082 |
| Operating cash flow (OCF) | (115) | 90 | 225 | 829 | 1,309 |
| Development and maint. capex | (682) | (2,866) | (10,216) | (4,618) | (531) |
| Capitalized interest | 0 | 0 | (176) | (293) | (110) |
| Free cash flow (ex prepay) | (797) | (2,776) | (10,168) | (4,082) | 668 |
| Net financing cash flow | 875 | 6,877 | 7,144 | 3,922 | 106 |
| Capex / Adjusted revenue | 473% | 531% | 1068% | 186% | 16% |
| As of 31 May | FY25A | FY26A | FY27E | FY28E | FY29E |
|---|---|---|---|---|---|
| Cash (FY25A–FY26A excl. restricted)** | 42 | 1,592 | 1,117 | 957 | 1,731 |
| Property and equipment, net | 1,276 | 4,236 | 14,477 | 18,771 | 18,450 |
| Total assets | 1,870 | 9,929 | 17,293 | 21,426 | 21,880 |
| Total debt (carrying)‡ | 702 | 5,034 | 11,075 | 14,348 | 14,388 |
| Other liabilities and leases | 535 | 1,151 | 1,530 | 1,530 | 1,530 |
| Macquarie and Series E-1 pref. | 136 | 2,019 | 3,203 | 4,302 | 4,919 |
| Common equity (incl. NCI) | 498 | 1,725 | 1,484 | 1,246 | 1,042 |
| Net debt + Macq. pref.** | 660 | 5,398 | 13,450 | 17,982 | 17,865 |
| Fiscal year ending May | FY25A | FY26A | FY27E | FY28E | FY29E |
|---|---|---|---|---|---|
| EPS after pref. PIK ($) | (1.16) | (0.91) | (1.95) | (1.25) | (1.03) |
| Adjusted EPS (co. basis, $) | n.a. | n.a. | (0.05) | 0.68 | 1.10 |
| Book value per share ($) | 2.18 | 5.87 | 4.83 | 3.99 | 3.28 |
| Free cash flow per share ($) | (3.96) | (10.09) | (33.73) | (13.17) | 2.12 |
| Weighted basic shares (m) | 201.2 | 275.2 | 301.5 | 309.9 | 315.0 |
| Contracted MW in service (end)§ | 0 | 100 | 600 | 1,435 | 1,660 |
| Contracted rent / MW ($m)¶ | n.a. | n.a. | 1.73 | 1.69 | 1.71 |
| Portfolio NOI margin (%) | n.a. | 90.6% | 87.4% | 86.5% | 86.0% |
Margins reach 68% by FY29E, yet our EPS sits $0.50–$0.90 below consensus
| Measure (%) | FY25A | FY26A | FY27E | FY28E | FY29E |
|---|---|---|---|---|---|
| Growth | |||||
| Adjusted revenue growth | n.a. | 274.3% | 77.3% | 159.9% | 33.7% |
| Adjusted EBITDA growth | n.a. | 446.3% | 326.0% | 222.3% | 53.7% |
| Core EBIT growth* | n.m. | n.m. | n.m. | 612.4% | 67.5% |
| EPS after pref. PIK growth | n.m. | n.m. | n.m. | n.m. | n.m. |
| DPS growth | 0.0% | 0.0% | 0.0% | 0.0% | 0.0% |
| Margins and Coverage | |||||
| Portfolio NOI margin (% base rent) | n.a. | 90.6% | 87.4% | 86.5% | 86.0% |
| Adjusted EBITDA margin | 13.6% | 19.9% | 47.7% | 59.2% | 68.0% |
| Core EBIT margin* | −50.1% | −43.8% | 10.3% | 28.4% | 35.5% |
| Free cash flow margin | −553% | −514% | −1063% | −164% | 20.1% |
| EBITDA / net interest (x) | 1.3x | 3.6x | 1.7x | 2.3x | 2.4x |
| Measure | FY25A | FY26A | FY27E | FY28E | FY29E |
|---|---|---|---|---|---|
| Returns and Leverage | |||||
| Return on equity (ROE) | −47.0% | −14.5% | −39.6% | −31.1% | −31.1% |
| Return on assets (ROA) | −12.5% | −2.5% | −3.4% | −1.8% | −1.5% |
| Return on capital (ROCE) | −5.6% | −3.3% | 0.7% | 3.7% | 6.2% |
| Net debt / common equity | 133% | 200% | 694% | 1102% | 1247% |
| Net debt + Macq. pref. / EBITDA† | 33.6x | 50.3x | 29.4x | 12.2x | 7.9x |
| Valuation (at $12.22) | |||||
| P/E (adjusted EPS) | n.m. | n.m. | n.m. | 17.9x | 11.1x |
| EV / Adjusted EBITDA | 408.4x | 74.7x | 17.5x | 5.4x | 3.5x |
| FCF yield (%) | −21.6% | −75.2% | −275.3% | −110.5% | +18.1% |
| Dividend yield (%) | 0.0% | 0.0% | 0.0% | 0.0% | 0.0% |
| P/E at our target ($11.38, adj.) | n.m. | n.m. | n.m. | 16.7x | 10.3x |
| Metric (GAAP Revenue $m; EPS $) | FY27E | FY28E | FY28E Adj. EBITDA |
|---|---|---|---|
| Revenue ($m, GAAP basis including ChronoScale) and Adjusted EBITDA | |||
| Penmark estimate | 1,123 | 2,653 | 1,472 |
| Consensus (S&P Global: 9–10 est.; EBITDA: median of three Street data points) | 958 | 1,870 | 1,190 |
| Prior-year period (FY26A / Penmark FY27E*) | 611 | 1,123* | 457* |
| Penmark vs consensus (%) | +17.3% | +41.9% | +23.7% |
| Penmark projected y/y growth | +83.7% | +136.3% | +222.3% |
| EPS ($, Penmark core after preferred PIK vs S&P Global consensus) | |||
| Penmark estimate (EPS after preferred PIK) | (1.95) | (1.25) | n.a. |
| Consensus (S&P Global) | (1.06) | (0.71) | n.a. |
| Prior-year period (FY26A / Penmark FY27E*) | (0.91) | (1.95)* | n.a. |
| Penmark vs consensus ($) | −$0.89 | −$0.54 | n.a. |
| Penmark projected y/y change | n.m. | n.m. | n.a. |
Source: Company filings; median of three Street data points (FY28E); Penmark Research estimates
Why we sit above on EBITDA yet below on EPS. Our model incorporates all 1.56 GW of contracted leases plus an 80% probability on Polaris Forge 2’s 100 MW expansion, lifting FY28E GAAP revenue 42% above S&P Global consensus and EBITDA 24% above the median of three Street data points (Needham, Citizens, MarketScreener).
Below the line, capital costs dominate. Total debt reaches $14.7bn by FY28E (including $8.3bn of new project debt) alongside $4.2bn of accreting Macquarie 12.75% PIK preferred units, creating $1.1bn of combined FY28E net interest and preferred charges (with interest net of capitalized interest) that keep EPS after preferred PIK negative through FY31E.
Discount to AI-landlord peers reflects financing leverage, not mispriced capacity
| Metric (24 Nov 2026) | APLD | AI Peers* | DC REITs† | vs AI |
|---|---|---|---|---|
| Scale and Risk Profile | ||||
| Market cap ($bn) | 3.69 | 5.02 | 80.44 | −26% |
| Enterprise value ($bn) | 8.02 | 8.68 | 102.49 | −8% |
| Levered equity beta‡ | 3.50 | 4.28 | 0.99 | n.a. |
| Net debt / market cap | 82% | 102% | 28% | −20pp |
| Valuation Multiples (at Actual Price) | ||||
| EV / CY27E Revenue§ | 4.0x | 9.0x | 11.6x | −56% |
| EV / EBITDA (FY28E / CY26E) | 5.4x | n.m. | 22.5x | n.a. |
| Fully funded EV / FY30E EBITDA (REITs CY26E) | 9.1x | n.a. | 22.5x | n.a. |
| Price / Book (MRQ) | 2.3x | 3.8x | 4.5x | −39% |
| Profitability and Returns | ||||
| Adjusted EBITDA margin (steady)§ | 68.0% | 8.8% | 51.5% | +59pp |
| Dividend yield | 0.0% | 0.0% | 2.5% | 0.0pp |
| Fully funded EV / leased MW | $12.9m | n.a. | n.a. | n.a. |
| Date | Catalyst and Penmark Expectation |
|---|---|
| Dec 26–Mar 27 | PF2 200 MW RFS and +100 MW lease: First 25 MW live 24 Nov; remaining 175 MW RFS and expansion lease at >15% rent uplift ($2.79/sh vs unleased). |
| ~6 Jan 2027 | Q2 FY27 earnings (expected): First read on PF1 Building 2 ramp, NOI margin durability (guide 88%) and cash burn run-rate. |
| 1H CY27 | 810 MW project debt closings: Debt pricing (≤8.5%) and loan-to-cost (80% LTC) on DF1, PF3 and DF2 validate funding model. |
| Apr–Oct 27 | DF1 B1, PF1 B3, PF2 exp. and PF3 B1 RFS (550 MW): On-time delivery tests $12m/MW capex discipline and unlocks $1bn+ annualized NOI target. |
| Direction | Risk and Per-Share Impact |
|---|---|
| Upside (+$5.62) | WACC drops 100bp to 7.74%: Lower rates or tighter spreads lift Base value to $12.79 (Buy, +20% 12m return) and squeeze shorts. |
| Upside (+$7.73) | CPI-linked rent escalators (1.5%/yr): Unmodeled variable escalators in hyperscaler leases lift Base value to $14.90. |
| Downside (−$3.09) | Capex hits $13.5m/MW: Build-cost overrun to Meta Hyperion benchmark drops Base value to $4.08 and widens funding gap. |
| Downside (−$5.27) | Lease renewal shock: 50% renewal at 80% rent (vs 80% at flat rent) cuts Base value to $1.90. |
| Downside (−$1.97) | CoreWeave credit stress: 25% PF1 rent cut (vs 7.5% base loss) drops Base value to $5.20. |
Source: Company filings; Yahoo Finance monthly closes to 24 Nov 2026
Reading the bands: Standard-deviation bands measure how far trailing Price-to-Book sits from its 2-year mean (5.1x). Book equity shrinks as Macquarie PIK accrues.
Source: Yahoo Finance trailing metrics (24 Nov 2026); APLD FY26A GAAP revenue
Consistent trailing basis: Global peers span 3.2x (GDS) to 19.1x (NXT.AX) with no linear margin fit. APLD’s 13.1x FY26A multiple compresses to 4.0x CY27E revenue as capacity ramps, though $13.2bn of remaining capex sits ahead of equity.
Six charts: the stock tracked signed gigawatts until financing costs took over
Source: Company releases; Yahoo Finance month-end closes (May 2025 to 24 Nov 2026)
Lead driver broke after the 28 May 2026 peak: Contracted megawatts drove a 7x rally to $49.65 before capital-stack costs pulled shares down 75%.
Source: Penmark Research estimates
Why multiples mislead: Perpetuity multiples ignore higher cost of capital (−$8.81) plus taxes, stock-based pay and refresh capex (−$10.54).
Source: Company filings; Penmark Research estimates
Seniority wall: Debt principal ($14.4bn) and Macquarie 12.75% preferred ($5.5bn) absorb priority cash flows through FY30E.
Source: S&P Global via Yahoo Finance (25 Nov 2026); Penmark Research estimates
Revenue is not the bear case: Our GAAP revenue beats Street consensus by 17% to 42%, yet capital charges keep common EPS negative.
Source: Market prices as of 24 Nov 2026; StockAnalysis; Penmark Research estimates
Valuation discount explained: APLD trades below AI peers because $13.2bn of remaining build capex sits ahead of common equity.
Source: Penmark Research estimates
Asymmetric sensitivity: Lower WACC (−100bp to $12.79) or unmodeled rent escalators (+1.5%/yr to $14.90) lift base value above today’s price.
Five debates decide whether APLD is worth $0, about $7 or about $32
Three upside debates and funding timing explain $4.25 of the $5.05 gap between the $12.22 share price and our $7.17 base DCF, while two further debates test build cost and CoreWeave credit. Each debate below is mapped by name to our stock-driver analysis and thesis chapters, with dated signposts.
| Debate Name | Market / Street View | Penmark View | Key Evidence | What Changes Our View | Resolves |
|---|---|---|---|---|---|
| New Leasing and Valuation | Bulls such as Needham apply 19.5x–21x perpetuity EV/EBITDA to FY29E EBITDA (consensus target $56.67). | Finite 15–18yr leases require full-life DCF ($7.17 Base) capturing tax, SBC and refresh. | DCF sits 73% below our Street-style 13.5x reference ($26.52) on 8.74% WACC, FY33 tax and $2.6bn refresh. | Verified 1.5%+ CPI escalators or perpetual REIT re-rating at 7.84% WACC. | FY27E–28E |
| Cost of Capital and Funding | 80% loan-to-cost (LTC) debt and Macquarie preferred fund 810 MW at <8% cost. | $13.2bn build bill drives debt and PIK preferred to $19.9bn, trapping equity returns. | ComputeCo 1 priced at 9.25%, Macquarie accrues 12.75% PIK; 810 MW still unfunded. | 810 MW debt closes at ≤7.25% with zero parent guarantees or common dilution. | 1H CY27 |
| Build Cost and Schedule | Standardized AI factories hold $11–$13m/MW capex and hit all CY27–CY28 RFS dates. | Base uses $12m/MW on time, but skewed risk: $13.5m/MW cuts base equity sharply. | Meta Hyperion JV benchmarks at $13.5m/MW; 3 unquantified completion guarantees. | PF2 (200 MW) and DF1 B1 (150 MW) deliver on time at ≤$11.5m/MW total cost. | Dec 26–Apr 27 |
| Renewal and Residual Value | Hyperscalers renew 90% of capacity at flat rents; liquid-cooled shells last 30+ yrs. | 80% renewal at flat rent and $2.6bn refresh in Base; 50% renewal at 80% rent cuts value to $1.90. | AI silicon power density doubles every 2–3 yrs; remote ND sites lack metro network effects. | Long-term renewal options exercised early or secondary AI tenant demand in North Dakota. | CY27–CY28 |
| Counterparty and Governance | ~74% investment-grade (IG) tenants de-risk rent; insider buying signals alignment. | CoreWeave (~26% rent; 7.5% base loss) carries credit stress (2031 notes ~16%); $332m FY26 named executive officer (NEO) pay (grant-date value, DEF 14A) flags risk. | 17.59m CEO shares pledged; $100m Base Electron credit line; 5.25% ChronoScale management incentive plan. | CoreWeave IG upgrade, Base Electron note repaid, and SBC capped below $75m/yr. | Ongoing FY27 |
Source: Penmark Research estimates
Cost of Capital and Funding → Thesis Pillar 1 (p. 17) and Forecasts (pp. 21–22): Models the $13.2bn build bill, 80% LTC debt wall and Macquarie PIK waterfall.
New Leasing and Valuation / Renewal and Residual Value → Thesis Pillar 2 (p. 18) and Valuation (pp. 23–24): Deconstructs the $19.35/sh gap between our Street-style 13.5x reference and full-life lease DCF.
Build Cost and Schedule / Counterparty and Governance → Thesis Pillar 3 (p. 19): Stress-tests $13.5m/MW capex, CoreWeave credit concentration and related-party leakage.
Source: Company filings; Penmark Research estimates
$41bn of signed AI leases, $13bn left to spend and about $7 a share of base equity
In 18 months, a Dallas-based crypto host turned its sites into 1.56 GW of contracted artificial intelligence factories. About 57.7% is in the northern US (38.5% confirmed in North Dakota), 32.7% in the southern US and 9.6% at an undisclosed site. The twist is that signing the leases was the easy part; financing them hands the first $20 billion of value to lenders and Macquarie.
On a Monday morning in November 2026, Applied Digital announced an 18-year, 150-megawatt data center lease worth $5.4 billion, and its stock jumped 20% in a single session. Yet even after that rally, the shares sat 72% below their May peak of $49.65. Behind that paradox lies the central drama of modern artificial intelligence (AI) infrastructure: a small developer with 256 full-time employees has accumulated a $41 billion backlog across ten leases (six campuses), while carrying the construction balance sheet of a major utility.
Applied Digital builds and owns purpose-built, liquid-cooled data centers (which management calls AI factories) designed to house dense racks of graphics processing units (GPUs). Five years ago, the company hosted Bitcoin mining rigs in Jamestown and Ellendale, North Dakota. Those rural locations gave it something Silicon Valley and Northern Virginia no longer had: contiguous land next to high-voltage substations, abundant low-cost power and sub-zero winters that cut mechanical cooling loads.
Here is how the money comes in. Applied Digital sells long-term take-or-pay leases running 15 to 18 years to three investment-grade hyperscalers and CoreWeave. Tenants pay a fixed monthly base rent per megawatt of critical IT load, roughly $1.6 million to $2.0 million per megawatt-year, plus pass-through recoveries for power and property expenses. In FY26, high-performance computing (HPC) rent was just $100 million (18% of adjusted revenue), smaller than low-margin tenant fit-out work ($271 million) and legacy Bitcoin hosting ($154 million). Once all contracted campuses energize by FY30, HPC rent reaches $2.79 billion (81% of adjusted revenue), and every dollar of rent turns into about 86 cents of net operating income (NOI).
The turning point arrived in June 2025, when Applied Digital signed its first 250-megawatt HPC lease with CoreWeave at Polaris Forge 1 in Ellendale. Within twelve months, it added 150 megawatts for CoreWeave, broke ground on Polaris Forge 2 near Harwood and Delta Forge 1 in the southern US, and spun off its cloud unit into ChronoScale (keeping 96%). It also raised $1.8 billion from Macquarie Asset Management and $6.09 billion in senior secured notes (including $4.5 billion of 9.25% and 6.75% construction notes). Contracted capacity jumped from zero to 1.41 gigawatts by June 2026, and to 1.56 gigawatts on 23 November 2026.
The model works because grid interconnection queues in primary US markets now stretch two to four years. Hyperscalers desperate for powered shells sign 15-to-18-year commitments to lock in standardized 150-megawatt buildings delivered in 12 to 15 months. Once a tenant installs billions of dollars of liquid-cooled servers, switching landlords mid-lease is nearly impossible.
What could break that loop sits on the right-hand side of the balance sheet. Building each megawatt costs about $12 million, requiring $13.2 billion of further capital expenditure from September 2026 onward. To fund it without issuing common stock, Applied Digital borrows 80% of campus cost at 6.75%–9.25% and sells Macquarie 12.75% payment-in-kind (PIK) preferred equity plus 15% of campus common stock. That links directly to our Cost of Capital and Funding and Build Cost and Schedule debates: if debt slips six months or capex tracks Meta’s $13.5 million-per-megawatt benchmark, common equity absorbs the entire shock.
Why this story matters for the stock: Investors bid APLD to $49.65 when they valued step 2 in isolation; the 75% drawdown reflects the market confronting step 3’s funding bill and step 4’s thin common residual.
A five-year pivot from Bitcoin hosting to a 1.6 GW contracted AI landlord
Source: Company SEC filings and press releases
Source: Company filings; Penmark Research estimates (FY30E steady state)
Source: Company filings and releases to 24 Nov 2026; Penmark Research estimates
Two distinct operating segments, one dominant equity driver. Following the May 2026 separation of its GPU cloud unit into ChronoScale (NASDAQ: CHRN, 96% owned by APLD), Applied Digital reports two segments: HPC Hosting (AI factories) and legacy Data Center Hosting (286 MW of Bitcoin mining hosting across Jamestown and Ellendale). While legacy hosting provided $154m of revenue in FY26 and contributes about $57m a year of steady EBITDA in our forecast, it accounts for only about 4% of enterprise value ($285m of $8.02bn), leaving HPC as the dominant value driver.
Why tenant fit-out and build capex diverge sharply from EBITDA. Tenant fit-out services ($271m in FY26A; $183m in Q1 FY27A) inflate near-term revenue at just ~4.5% gross margin before disappearing once campuses open. Meanwhile, cash conversion is deeply negative during construction ($10.2bn FY27E FCF outflow) and only turns positive in FY29E ($668m), after $13.2bn of capex is funded through project notes and Macquarie preferred draws.
68% EBITDA margins still leave common holders with a loss after $1.7bn of capital charges
Source: Penmark Research estimates (FY30E steady state)
Operating economics are genuinely strong, but financing claims absorb them. At steady state in FY30E, Applied Digital, with base rent 81% of revenue, earns a 68.0% adjusted EBITDA margin ($2,337m, after a 7.5% CoreWeave expected loss), well above Digital Realty’s ~52% CY26E EBITDA margin because power is passed through and triple-net costs are lean. Yet $1,025m of net interest and $625m of FY30E preferred charges ($620m Macquarie PIK and $5.6m Series E-1) consume 134% of Core EBIT, keeping common EPS after preferred PIK negative through FY31E.
Source: Company filings; Penmark Research estimates
Model linkage: Every forecast year builds directly from the top branch above (active leased megawatts times contracted rent per megawatt-year), with no pipeline beyond the PF2 expansion. Platform cash general and administrative (G&A) costs rise from $70m in FY27E to $111m by FY30E (4% of base rent), creating strong operating leverage once campuses energize.
750 MW enters service within 12 months; 810 MW still lacks financing
Source: Company filings, Q4 FY26 call; Penmark Research estimates
| Campus | Region | Tenant | MW | Term | Rent/MW | NOI Mgn | Model RFS | Funding Status |
|---|---|---|---|---|---|---|---|---|
| Polaris Forge 1 | Ellendale, ND | CoreWeave | 400 | 15 yr | $1.76m | 88.0% | Oct 25–Jul 27 | Funded (9.25% / 7.00% notes) |
| Polaris Forge 2 | Harwood, ND | Hyperscaler B (IG) | 200 | 15 yr | $1.67m | 86.0% | Dec 26–Mar 27 | Funded (6.75% notes) |
| Delta Forge 1 | Southern US | Hyperscaler A (IG) | 300 | 15 yr | $1.67m | 85.0% | Apr 27–Feb 28 | Debt Unfunded ($300m bridge) |
| Polaris Forge 3 | Northern US (undiscl.) | Hyperscaler A (IG) | 300 | 15 yr | $1.67m | 85.0% | Oct 27–Oct 28 | Project debt Unfunded |
| Delta Forge 2 | Southern US | Hyperscaler A (IG) | 210 | 15 yr | $1.65m | 85.0% | Apr 2028 | Project debt Unfunded |
| Nov 2026 Lease | Undisclosed | IG Hyperscaler | 150 | 18 yr | $2.00m | 85.0% | May–Nov 28 | Project debt Unfunded |
| PF2 Expansion (80%) | Harwood, ND | Unleased | 80* | 15 yr | $1.92m | 86.0% | Sep 2027 | Shell funded (6.75% notes) |
| Total Portfolio | Northern, southern, undisclosed | 4 Counterparties | 1,640 | 15–18y | $1.70m‡ | 85.9% | Oct 25–28 | 600+80* funded / 810 Unfunded† |
Source: Company filings, Q4 FY26 call; Penmark Research estimates
Customer concentration is structural. Only four HPC tenants account for 100% of the $41bn+ lease backlog, and Marathon is the largest customer in the 286 MW legacy Bitcoin hosting business segment. While three investment-grade hyperscalers anchor ~74% of contracted HPC rent, CoreWeave’s ~26% contracted share (400 MW at PF1; 23% in FY30E net of our 7.5% expected loss) remains non-investment-grade and represents Applied Digital’s earliest cash flow.
1% vacancy and 24–48 month grid queues drive frontier AI leasing, yet supply is surging
North American data center demand has outpaced grid supply for three consecutive years. According to CBRE, primary-market inventory reached 9.43 GW at year-end 2025 (+36% y/y), while annual net absorption hit a record 2.50 GW and vacancy dropped to a record-low 1.4%. Tightness persisted into Q1 2026, with vacancy falling to 0.3% in Northern Virginia, 1.0% in Atlanta, 1.8% in Dallas–Fort Worth and 2.2% in Chicago. At roughly $1.7m–$2.0m per MW-year of base rent, North American primary markets already represent ~$16bn–$19bn of annual rent, expanding by $4bn+ per year.
Power procurement, not land or concrete, is the binding constraint. The Congressional Research Service notes that new generation and transmission infrastructure typically takes years longer to construct than data centers. CBRE estimates grid interconnection queues now run 24 to more than 48 months in primary hubs, pushing preleasing into the mid-70% range versus a 40%–50% historical norm.
The frontier migration creates both APLD’s window and its long-term risk. JLL reports roughly 1% vacancy at midyear 2026 alongside more than 66 GW under construction across broader North America, with 77% (about 51 GW) located in frontier markets outside traditional hubs. While grid scarcity gave Applied Digital pricing power on 1.56 GW of northern and southern US leases ($1.65m–$2.00m/MW-yr), roughly 51 GW of incoming frontier supply threatens renewal pricing when leases expire in the early 2040s.
Cap rates and build costs reveal a tightening spread. CBRE places Class A data center cap rates at 100–150 bp over the 10-year US Treasury (4.92% on 23 Nov 2026), implying ~5.9%–6.4% stabilized yields for prime metro assets. Frontier single-tenant AI builds require wider spreads (~250 bp over Treasury, a 7.4% cap rate), while our lease DCF uses an 8.74% WACC (the roughly 130 bp gap accounts for −$8.81/sh in Exhibit 18) as build costs approach $12m–$13.5m/MW.
Source: Company filings; CBRE; JLL; Penmark Research estimates
Source: CBRE North America Data Center Trends (YE25 and Q1 2026)
| Indicator | Reading | Period / Source |
|---|---|---|
| Primary-market supply | 9.43 GW | YE 2025 (CBRE) |
| Primary net absorption | 2.50 GW | FY 2025 (CBRE) |
| Primary under construction | 5.99 GW | YE 2025 (CBRE) |
| Broader NA construction | >66 GW | 1H 2026 (JLL) |
| 3–10 MW asking rent y/y | +12.5% | YE 2025 (CBRE) |
| Class A cap-rate spread | +100–150bp | over 10y UST |
| Grid interconnect queue | 24–48+ mo | 2026E (CBRE) |
Strong speed-to-power advantage is offset by a structural cost-of-capital deficit
Applied Digital competes across three distinct landlord tiers for hyperscaler AI capacity. First are blue-chip data center real estate investment trusts (REITs) such as Digital Realty (DLR) and Equinix (EQIX), which enjoy investment-grade balance sheets (borrow at about 5.0%–5.5%) and dense metro network ecosystems, but face scarce gigawatt-scale power. Second are private capital platforms, such as Aligned Data Centers (acquired by GIP/MGX/AIP for $40bn in October 2025) and Blue Owl’s $27bn Meta Hyperion JV, backed by sovereign and pension equity.
Third are converted Bitcoin miners (CORZ, WULF, CIFR, HUT) and the neocloud Nebius (NBIS), APLD’s closest listed peer set. Core Scientific, TeraWulf, Cipher Digital, Hut 8 and Nebius repurpose power-rich crypto sites or build GPU campuses for AI workloads. Against this cohort, Applied Digital leads in contracted hyperscale scale (1.56 GW across 3 IG hyperscalers + CoreWeave) and repeatable 150 MW liquid-cooled building delivery.
How hyperscalers choose a landlord: speed first, then reliability and price. In FY25–FY26, hyperscalers prioritized time-to-energization above all else, allowing APLD to win ten multibillion-dollar leases across six campuses with master service agreements that are difficult for unproven developers to obtain. Recent pricing momentum confirms tight near-term supply: the November 2026 150 MW lease priced at $2.0m/MW-yr, ~20% above early PF2/DF1 deals ($1.67m/MW-yr).
Why the moat narrows after the initial lease term. Applied Digital’s advantages (early utility interconnects, cold-climate cooling efficiency and ABB/BASX/Caterpillar bulk procurement) are real execution edges during construction. However, it lacks the network-effect interconnection moat of Equinix. It also pays about 125–425 bp more for project debt (6.75%–9.25%) and 725–775 bp more for Macquarie preferred (12.75% PIK) than investment-grade REITs (5.0%–5.5% debt). Those observable funding spreads leave a lasting financing deficit once grid queues normalize.
Source: Company filings; Penmark Research assessment
Source: Company filings; Penmark Research estimates
- High mid-lease switching costs (Durable 15–18 yrs): Once hyperscalers deploy $3bn–$5bn of liquid-cooled GPUs inside PF2 or DF1, take-or-pay covenants lock base rent through ~FY41–FY47.
- Standardized 150 MW build franchise (Medium-term): Qualifying with three IG hyperscalers and securing ABB, BASX and Caterpillar supply lines separates APLD from smaller crypto miners.
- Cost-of-capital gap (Structural headwind): Issuing 6.75%–9.25% project notes and 12.75% Macquarie PIK equity means APLD surrenders value on every new GW compared with REITs or Blue Owl.
- No metro network effect (Long-term risk): Unlike Equinix’s fiber-dense hubs, rural North Dakota AI training campuses face commoditization once about 51 GW of frontier capacity (77% of >66 GW NA construction) energizes.
FY26 NEO pay hit about $330m (grant-date value, DEF 14A) alongside related-party dealings
| 1. Who | 2. Tenure and Background | 3. How They Are Paid (FY26 DEF 14A) | 4. What They Own (at $12.22) |
|---|---|---|---|
| Wes Cummins CEO and Chairman (49) Founder Pledged |
5.7 yrs as CEO (Mar 2021); sole officer 2012–20; 19 yrs at co. Prior: 272 Capital (founder), B. Riley. Also CEO of Base Electron. | $189.2m total ($0.88m sal, $1.20m bon, $185.90m eq, $1.24m other incl. $1.09m jet). Metrics: FY26 discretionary (200% bon) + PSUs tied to MW signed, financing and NOI; FY27 Cash AEBITDA. | $285.5m (23.36m shs; 7.7% of 302.3m basic; 324x sal). 17.59m shs pledged to JPMorgan. Form 4: sold 630k @ $27.39 (Jul 26); bought 56k @ $18.04 (Oct 26). |
| Jason Zhang President and Co-Founder (34) Founder New <12m |
0.9 yrs as President (Jan 2026); CSO Aug 2025; co-founded 2021. Prior: Valuefinder, Sequoia Capital, MSD Capital. President of Base Electron. | $100.0m total ($0.69m sal, $0 bon, $99.33m eq, $0.02m other). Metrics: 1.5m PSUs vest on 600 MW IG / 1.6 GW total signed and RFS hurdles (0% tied to per-share ROIC). | $31.0m (2.54m shs; 0.84% out; 45x sal). Form 4: sold 236k @ $27.39 (Jul 26); bought 300k @ $18.86 ($5.7m, Oct 26). |
| Saidal Mohmand Chief Financial Officer (36) |
2.1 yrs as CFO (Oct 2024); 5.2 yrs at co. (EVP Finance Sep 2021). Prior: 272 Capital, B. Riley Asset Mgmt, GrizzlyRock Capital. | $40.5m total ($0.53m sal, $1.11m bon, $38.64m eq, $0.21m other incl. $91k jet). Metrics: FY26 discretionary (57% bon after $750k sign-on) + RSUs, PSUs and ChronoScale incentive units. | $10.9m (0.89m shs; 0.29% out; 21x sal). Form 4: sold 96k @ $27.39 ($2.6m, Jul 26); RSU vest Oct 26. |
| Laura Laltrello Chief Operating Officer (53) |
1.9 yrs as COO (Jan 2025); 1.9 yrs at co. Prior: Honeywell (VP/GM Building Automation, 2020–24), Lenovo (VP Global DC Services, 2005–20). | $2.6m total ($0.53m sal, $0.22m bon, $1.84m eq, $0.05m other). Metrics: FY26 annual bonus (49% target) + service RSUs and ChronoScale incentive units (joined FY25). | $9.9m (0.81m shs; 0.27% out; 19x sal). Form 4: sold 261k @ $27.39 ($7.1m, Jul 26). |
Pay rewards megawatt volume, not capital efficiency. Named executive officer (NEO) pay reached $332.4m in FY26 (grant-date value, DEF 14A; exceeding FY26 GAAP SBC expense of $220.1m because multi-year awards amortize over vesting), with 98% delivered in equity awards vesting on gross MW signed and energized rather than return on invested capital (ROIC) or free cash flow per share. That structure incentivizes signing gigawatts even when 80% debt and 12.75% PIK preferred leave thin residual equity value.
Board structure and insider signaling. Five of six directors are independent, with Douglas Miller as Lead Independent Director countering the combined CEO/Chair role, and a clawback policy is in place. Insiders own 9.5% of shares; notably, Cummins and Zhang sold $23.7m at $27.39 in July 2026 before buying $6.7m on the open market at $18.04–$18.86 in October 2026.
1. Base Electron ($100m Grid Note and $37m payment): An independent power developer owned and run by CEO Cummins and President Zhang (APLD owns ~10%). APLD unconditionally guaranteed a $2.4bn Babcock & Wilcox (B&W) build contract (terminated May 2026 after paying $37.0m on Base Electron’s behalf) and extended a $100m demand Grid Note ($59.3m drawn as of 31 Aug 2026).
2. ChronoScale incentive units (5.25% transfer): In April 2026, the board granted management fully vested Management Incentive Plan units equal to 5.25% of APLD’s ChronoScale shares, while APLD extended a $100m credit line to ChronoScale ($7m drawn).
3. Pledged stock and perquisites: 17.59m of CEO Cummins’s 23.36m shares (75%) are pledged to JPMorgan Chase (margin-call risk after a 75% drawdown), alongside $1.09m of personal private aircraft use in FY26.
Source: Company SEC Form 10-K cash flow statements (FY22A-FY26A)
Share count is up almost 5x since FY22, and returns on capital stay below our 8.7% cost of capital
Source: Company SEC Form 10-K filings (FY22A to FY26A)
Dilution overhang: Even with zero new equity modeled in our base case, 15.3m unvested RSUs/PSUs, 28.1m warrants (all warrants at $7.19–$10.75) and 46.1m convertible shares cap upside.
Source: Company filings; Penmark Research estimates
Economic spread is negative after D&A and SBC: Gross NOI yields ~11.9% on $12m/MW build cost, but after depreciation ($1.0bn), G&A and SBC, core ROCE peaks at 6.8%, about 190bp below WACC.
| Management Target / Guide | Company Guidance | Actual / Penmark Base | Track Record | Allocation Implication |
|---|---|---|---|---|
| Critical IT live in ND | 300 MW by 31 Dec 2026 | 275 MW live 24 Nov 2026 | On track | PF2 first 25 MW energized 24 Nov; 25 MW left for YE26. |
| PF1 initial RFS and NOI margin | 100 MW Oct 25; 85%–91% NOI | 275 MW live 24 Nov (incl. PF2 25 MW); 89.4% NOI | Beat early | Strong execution on first 250 MW in Ellendale. |
| Expansion leasing and rent | 225–275 MW YE26; >15% uplift | 150 MW signed Nov 2026 (+20%) | On track | Nov 2026 lease at $2.0m/MW-yr confirms pricing power. |
| Build capex per MW | $11m–$13m / MW | $12.0m Base (Meta $13.5m) | Unproven | 275 MW live 24 Nov; 1,285 MW contracted (1,385 MW incl. PF2 exp.) still to build. |
| Q1 FY27 capex guide | ~$600m cash capex | $2,074.7m reported | Missed | Driven by payables paydown ($556m accrued capex at 31 May 2026). |
| 810 MW + 150 MW Nov lease | 80% LTC; Macquarie 75% eq. | $8.7bn new debt FY27–29 | Pending | Funds DF1, PF3, DF2 and Nov 2026 lease; slippage triggers Bear. |
| Annualized NOI run-rate | $1.0bn run-rate (~Jul 27) | $1.12bn ($2.39bn FY30E) | On track (base) | Met in Base once PF1, PF2 and DF1 B1 energize. |
| CY2030 operating portfolio | 3.5–4.0 GW by end CY30 | 1.66 GW gross (1.64 GW wtd) | Not in base | Excluded: 810 MW unfinanced (plus 150 MW Nov lease) and new power starts 2030+. |
| ChronoScale cloud ARR | $1.0bn ARR in CY2027 | $166m Q1 annualized ($41.5m) | 6x gap | Valued at 50% ($618m): 96% block in 4% float illiquid. |
What Management and Governance Mean for Per-Share Value
Management deserves credit for commercial execution, but capital allocation has transferred value away from common shareholders. Securing 1.56 GW of AI leases (three hyperscalers and CoreWeave) in 18 months is an extraordinary commercial feat. Yet funding those leases through 6.75%–9.25% debt, 12.75% Macquarie PIK preferred, 15% campus common leakage, 4.8x share dilution and $332m of FY26 NEO pay (grant-date value, DEF 14A) means the platform expanded while per-share base value is only $7.17.
Governance discount is warranted until incentives align with per-share returns. Until Applied Digital caps SBC below $75m/year, winds down the $100m Base Electron related-party credit line, and ties PSU vesting to ROIC and FCF per share rather than gross MW signed, we see no case for valuing APLD on a REIT multiple.
APLD trades on lease signings and AI-landlord multiples, not quarterly GAAP earnings
Quarterly earnings barely move APLD (+0.2% to +0.9% on the last two prints), whereas lease announcements and credit sell-offs dominate. Major leases lifted shares up to +48.5%, while AI-credit sell-offs drove −17.8% and −11.6% drops. Comparing market reactions against our lease DCF explains why base value sits below price while a 20% bull weight anchors our Hold rating.
| Confirmed Driver | What Moves the Stock | Tests Passed | Market Move vs Model $/sh | Linked Debate | Next Number to Watch |
|---|---|---|---|---|---|
| Lease Origination and Pricing | Signed MW announcements and rent/MW vs $1.67m baseline | 3 of 4 tests (Events, Decomposition, Q&A 76%) | 23 Nov 2026 150 MW: +$2.33/sh (+20%); moving the PF2 100 MW expansion from 80% to 100% probability adds about $0.70/sh | New Leasing and Valuation | PF2 100 MW lease by Mar 2027 (Est $1.92m/MW) |
| AI-Landlord Sector Multiple | Peer EV/Rev and CoreWeave beta (45% weekly variance) | 3 of 4 tests (Factor R², Decomposition, Q&A) | 1Y peer basket drop explains APLD’s −48.6% 1Y decline | New Leasing and Valuation | CoreWeave credit spreads and peer EV/Rev (daily) |
| Project Financing and Cost of Capital | Debt LTC/coupon on 810 MW unfunded build and WACC | 2 of 4 tests (Q&A 30%, Event reactions) | Market prices 7.84% WACC vs Penmark 8.74% (−$5.05/sh gap, −41%) | Cost of Capital and Funding | DF1/PF3 project debt close, 1H CY27 (Est 7.5%) |
| Construction Capex and Delivery | Capex/MW vs $11–$13m guide and 750 MW RFS milestones | 2 of 4 tests (Q&A 35%, Event reactions) | Price implies $9.8m/MW vs our $12.0m base (a $13.5m/MW stress costs $3.09/sh) | Build Cost and Schedule | PF2 200 MW live RFS, Mar 27 (Est $12m/MW) |
Source: Yahoo Finance event-day closes; company press releases
Key takeaway: Once PF1/PF2/DF1 leases were signed, pure quarterly GAAP earnings stopped moving APLD (+0.9% Jul 2026, +0.2% Oct 2026); lease headlines lift shares up to +48.5% (PF2 fell −5.9%), while AI sell-offs hit −17.8% (20 Nov 2026) and −11.6% (24 Nov 2026).
Source: Yahoo Finance; company filings to 24 Nov 2026 (compounded)
2Y and 12M peer check: Over 2 years (Nov 2024 to Nov 2026), APLD rose +14.4% vs AI-landlord peers +15.3%, driven by lease re-rating before 2H 2026 compression. Over 12 months (Databento), APLD (−48.6%) trailed DC REIT DLR (+3.9%) but beat AI peers CIFR (−67.1%) and IREN (−73.6%).
Source: Yahoo Finance; Penmark Research estimates
Leases and the AI-landlord sector move the stock; Bitcoin and quarterly EPS do not
Source: Weekly returns Apr 2025 to Nov 2026 (n=87, R²=44.5%); *p < 0.05; others not significant
Source: Five earnings call transcripts (Q1 FY26 to Q1 FY27); topics overlap (sum 171%)
1. Lease Origination and Pricing (3 of 4 tests)
Market reaction: Major lease headlines drove swings from −5.9% (PF2) to +48.5% (PF1) and +20.3% (Nov 23) as investors capitalized headline rent.
Model value and gap: At $12m/MW capex and 8.74% WACC, senior claims cap per-share gains. Moving the PF2 100 MW expansion from 80% to 100% probability adds about $0.70/sh, and 300 MW of new leases adds $1.41/sh. Links to New Leasing and Valuation.
Next watch: PF2 100 MW lease by Mar 27 (Est $1.92m/MW; stock ±10–15%).
2. AI-Landlord Sector Multiple (3 of 4 tests)
Market reaction: AI-landlord peers (β +0.56) and CoreWeave (β +0.38) explain 45% of APLD’s weekly variance. Sector multiple compression drove the −48.6% 1Y drop.
Model value and gap: Peer EV/revenue (9.0x) ignores debt and preferred seniority. Moving from our 13.5x FY30E reference ($26.52) to Base DCF ($7.17) removes $19.35/sh. Links to New Leasing and Valuation.
Next watch: CoreWeave credit spreads and peer EV/Rev multiples (continuous).
3. Project Financing and Cost of Capital (2 of 4 tests)
Market reaction: Management hedged on debt timing across 30% of Q&A turns. Today’s price implies a 7.84% WACC despite 6.75%–9.25% notes and 12.75% PIK.
Model value and gap: Moving from 7.84% implied WACC to our 8.74% base cuts $5.05/sh (−41%). A 100bp WACC cut lifts base value above today’s price, while a 6-month funding slip cuts $1.07/sh. Links to Cost of Capital and Funding.
Next watch: DF1/PF3 project debt close in 1Q–1H CY27 (Est 80% LTC @ 7.5%).
4. Construction Capex and Delivery (2 of 4 tests)
Market reaction: Analysts spent 35% of Q&A on delivery schedules and transformer queues. Current shares imply $9.77m/MW capex versus $11m–$13m/MW guidance.
Model value and gap: Across 1,385 MW still to deliver (1,285 MW contracted plus 100 MW uncontracted PF2 expansion), each +$1m/MW overrun cuts $2.06/sh. Capex at $13.5m/MW cuts base value sharply, while $10.5m/MW adds meaningful upside (Exhibit 69). Links to Build Cost and Schedule.
Next watch: PF2 200 MW full RFS by Mar 27 (25 MW live 24 Nov).
| Dropped Candidate | Empirical Test Result | Why Dropped from Driver Framework |
|---|---|---|
| Bitcoin (BTC-USD) | β = +0.07 (p = 0.80); 0% Q&A | Legacy 286 MW crypto hosting is about 4% of EV ($285m of $8.02bn); market decoupled from BTC after June 2025 CoreWeave deal. |
| 10Y Treasury Weekly Δ | β = +0.13 (p = 0.32); 0 events | High-frequency yield moves get drowned by idiosyncratic lease/sector volatility, though absolute rate level sets WACC. |
| Quarterly GAAP EPS | +0.9% / +0.2% last 2 calls | Heavy capitalized interest, SBC and pre-RFS losses make quarterly GAAP EPS uninformative until FY28E. |
| ChronoScale Cloud ARR | 16% Q&A (hedged); 0 events | At $166m annualized ARR (vs $1bn 2027 guide) and 96%-owned ChronoScale structure, market applies steep illiquidity discount. |
A $13bn capex bill and senior claims leave about $7 a share in base DCF
Consensus capitalizes headline EBITDA at REIT-like rates instead of pricing finite lease cash flows. Street targets ($56.67 mean, 17 Buy) reflect frameworks such as Needham’s 19.5x–21x FY29E EBITDA, which capitalize EBITDA at about a 5% cap rate (about a 6.6% discount rate before growth). That sits far below our 8.74% WACC and omits cash taxes, future SBC, lease expiry and refresh capex. At $12.22, our reverse DCF implies a 7.84% WACC, 90 bp below our base hurdle.
Why seniority amplifies discount-rate sensitivity: Project-level senior notes, Macquarie’s 12.75% payment-in-kind (PIK) preferred equity (compounding by ~$620m/year by FY30E) and Macquarie’s 15% common interest in funded campuses sit strictly ahead of APLD’s public common stock.
(i) Q1 FY27 Form 10-Q balance sheet and commitments: At 31 August 2026, APLD held $3.68bn in cash and restricted cash against $6.09bn senior secured notes, $0.45bn convertible notes, $0.29bn other debt and leases, $2.01bn Macquarie preferred and $0.06bn Series E-1 preferred. Total build cost for 1,660 MW is $19.92bn; with $6.73bn spent, $13.19bn of development capex remains across FY27E–FY29E.
(ii) Project debt pricing and Macquarie structure: Recent campus financings carried 6.75%–9.25% coupons while Macquarie’s preferred compounds at 12.75% PIK plus 15% of campus common equity. Even at 80% LTC project debt ($8.7bn new debt modeled), net debt plus preferred peaks at $18.0bn in FY28E (12.2x FY28E EBITDA) and falls to $17.2bn, or 7.4x FY30E EBITDA, by FY30E (page 28).
(iii) Management Q&A hedging on 810 MW funding: Across 30% of analyst Q&A turns on FY26–FY27 calls, management hedged on closing timelines and spreads for DF1, PF3 and DF2, confirming financing for 810 MW remains uncommitted.
Source: Company filings (31 Aug 2026); Penmark Research estimates
A 100 bp WACC cut to 7.74% lifts base DCF 78% to $12.79, above the price (Buy on a +20% 12-month return), while a 100 bp rise cuts value by two-thirds (Sell). Because debt and preferred absorb $9.38bn of senior claims before common sees a dollar, APLD behaves like a deeply levered option on WACC and debt execution. Raising WACC from the market-implied 7.84% to our 8.74% base removes $5.05/sh (−41%); a +50 bp shock cuts $2.48/sh; and a 6-month slip costs $1.07/sh. Equity falls to $0 in our Bear case (30% weight, where financing, capex, CoreWeave rent and renewals move together) and also at APLD’s one-year regression beta (11.84% WACC).
| Date | Thesis Confirmed If… | Thesis Broken If… |
|---|---|---|
| 1Q CY27 | DF1/PF3 project debt prices >8.5% or LTC <75%, forcing equity issuance. | DF1/PF3 closes at 80% LTC and ≤7.25% fixed without warrants or PIK. |
| 2Q CY27 | Macquarie pref passes $3.3bn (above our $3.15bn FY27E base) with no refi path. | APLD refinances 12.75% Macquarie PIK into sub-7.5% REIT-style debt. |
| 2H CY27 | Interest + PIK exceeds 80% of FY28E EBITDA (above our ~77% base) or 10Y >5.25%. | Interest + PIK falls below 65% of FY28E EBITDA as WACC nears 7.7%. |
Our Street-style 13.5x multiple overstates value by about $19 a share
Sell-side bulls value APLD like a perpetual, tax-exempt data center REIT. Consensus averages $56.67 (range $22–$93), led by bulls such as Needham applying 19.5x–21x FY29E EBITDA (Needham, ~5% implied cap rate). Our own Street-style reference at 13.5x FY30E EBITDA ($2.34bn, a 7.4% cap rate = 10y UST + 250bp) produces $26.52/sh, 270% above our DCF base.
Why the multiple shortcut breaks down: A perpetual EV/EBITDA multiple assumes (1) zero corporate tax (REIT status APLD does not hold), (2) zero future stock compensation, (3) 100% rent renewal in perpetuity with zero refresh capex, and (4) a 7.4% discount rate rather than APLD’s 8.74% WACC.
(i) C-corp tax structure and NOL exhaustion: Unlike Digital Realty and Equinix, Applied Digital is a taxable C-corporation. Once accumulated net operating losses (NOLs) and bonus depreciation exhaust in FY32E, cash taxes begin in FY33E (23% marginal tax rate), forming a major share of the −$10.54/sh omitted-cash-flows gap in Exhibit 18.
(ii) Recurring SBC and corporate G&A leakage: Adjusted EBITDA strips out stock-based compensation ($220m in FY26A). Even modeling a sharp step-down to $75m/yr of future recurring grants (growing 3% annually), future SBC is one of the cash costs inside the −$10.54/sh omitted-cash-flows gap (Exhibit 18).
(iii) Finite lease life and FY41–FY48 refresh capex: All ten signed lease base terms expire between FY41 and FY47. Single-tenant AI training halls in rural North Dakota face technological obsolescence (power density/cooling shifts), requiring about $2.6bn of renewal refresh capex running into FY48E and carrying material re-leasing risk (80% base renewal, 50% bear).
Source: Penmark Research estimates (FY30E to FY50E HPC DCF)
Source: Penmark Research estimates
Even 100% renewal at 120% rent ($11.96) sits below $12.22: Without unmodeled annual CPI escalators (0.99% market-implied; escalator terms are not disclosed in the 10-Q), renewal optimism alone cannot justify today’s share price; 50% renewal at 80% rent cuts value to $1.90/sh.
Our $7.17 DCF base sits $19.35/sh below our Street-style 13.5x FY30E reference ($26.52) and $49.50/sh below Street consensus targets ($56.67). Independently, build cost gives $6.58/sh, 8% below the DCF; the gap is the development value created by the leases, whereas perpetual multiples omit rate, tax, SBC and asset decay.
| Date | Thesis Confirmed If… | Thesis Broken If… |
|---|---|---|
| ~6 Jan 2027 | Q2 FY27 10-Q still discloses no variable CPI escalators on Nov 2026 lease. | Management discloses 2%+ annual escalators across hyperscaler leases. |
| 2H CY27 | REIT conversion remains uneconomic due to C-corp tax and Macquarie pref. | APLD announces formal REIT election with tax-free spin structure. |
| FY27–28 | FY28E SBC expense exceeds our $150m forecast, or recurring new grants stay above $75m/yr. | SBC drops below $75m/yr and peers re-rate back above 14x EV/EBITDA. |
Build-cost inflation, CoreWeave concentration and governance friction cap re-rating
Bulls extrapolate early PF1 execution across 1.6 GW and dismiss governance red flags. Applied Digital energized 175 MW at Polaris Forge 1 by 31 August (Q1), 250 MW by October, and PF2’s first 25 MW on 24 November; PF1 ran at an 89.4% NOI margin in Q1 FY27. Consensus extrapolates that start across ten leases at $11m–$13m/MW, assumes CoreWeave pays $704m/yr cleanly for 15 years, and expects buyers to overlook executive pay and related-party lines once EBITDA inflects.
Why downside asymmetry dominates: APLD has given completion guarantees, which are not quantified in filings, meaning cost overruns and schedule delays hit common equity dollar-for-dollar, whereas upside rent gains accrue only on uncontracted future MW.
(i) Industry capex inflation and equipment lead times: CBRE and CRS document 24–48+ month substation/transformer queues and rising mechanical/electrical costs across North America. Meta’s Hyperion joint-venture benchmark sits at $13.5m/MW, against our $12.0m/MW base and the market-implied $9.8m/MW.
(ii) CoreWeave credit exposure (~26% of contracted rent): CoreWeave’s 9.75% 2031 notes yield ~16% with 5y CDS near 1,100–1,200bp; our base case models a 7.5% PF1 rent cut from FY30E ($651m/yr vs $704m contracted), and APLD’s weekly beta to CoreWeave is a statistically significant +0.38 (p < 0.05). As a levered GPU-cloud operator dependent on hyperscaler compute contracts, CoreWeave credit stress directly pressures APLD’s equity multiple.
(iii) FY26 DEF 14A governance and related-party audit: FY26 NEO pay of $332.4m (grant-date value, DEF 14A), 17.59m pledged CEO shares (75% of holdings), the $100m Base Electron Grid Note ($59.3m drawn; $37m B&W payment), and 5.25% ChronoScale incentive units deter long-only infrastructure funds.
Source: Penmark Research estimates
No cell reaches $12.22: Even $10.50m/MW build cost combined with +2.0pp NOI margin yields $11.85/sh, while a +12.5% overrun ($13.50m/MW) cuts base value by $3.09/sh to $4.08/sh (and CoreWeave −25% rent separately cuts $1.97/sh from the $7.17 base to $5.20/sh).
Source: Penmark Research estimates (change vs $7.17 base DCF)
Our 30% bear weight reflects the 810 MW still to finance in a widening AI-credit market. Execution risk sits in the bear-case drivers ($13.5m/MW capex, CoreWeave −25%) and the 7.5% base CoreWeave loss. Governance is not a model input; it is one reason for Low conviction. Even if Applied Digital delivers every megawatt on budget, the Base Electron credit line ($100m), 17.59m pledged CEO shares and $332m FY26 NEO pay (grant-date value, DEF 14A) weigh on institutional demand. Conversely, hitting $11m/MW capex and leasing PF2’s 100 MW at $1.92m/MW+ lifts equity value toward about $10/sh, still below $12.22.
| Date | Thesis Confirmed If… | Thesis Broken If… |
|---|---|---|
| Mar 2027 | PF2 RFS slips past 1Q CY27 or realized capex exceeds $13.0m/MW. | PF2 delivers 200 MW on time at ≤$11.5m/MW and leases +100 MW. |
| 2H CY27 | CoreWeave spreads widen >200 bp or DF1 encounters substation lag. | CoreWeave achieves IG rating or APLD diversifies CoreWeave <20%. |
| Sep 2027 | FY27 proxy shows NEO pay >$100m or Base Electron line expands. | Base Electron note repaid in full and CEO unpledges JPMorgan shares. |
The gap between adjusted EBITDA and GAAP operating income reached $340m in FY26 as cash burn hit $2.8bn
| Metric ($m, except per share) | FY22A | FY23A | FY24A | FY25A | FY26A | 4Y Trend |
|---|---|---|---|---|---|---|
| GAAP revenue (restated FY25) | 8.5 | 55.4 | 165.6 | 228.6 | 611.3 | 71.5x |
| GAAP revenue growth (%) | n.m. | +547.9% | +198.9% | +38.0% | +167.5% | HPC pivot |
| Adjusted revenue (ex ChronoScale) | n.a. | n.a. | n.a. | 144.2 | 539.7 | +274% FY26 |
| Profitability and GAAP-to-Adjusted Gap | ||||||
| GAAP operating income (EBIT)† | −20.9 | −44.1 | −98.3 | −72.2 | −236.5 | Widening |
| Adjusted EBITDA (company basis)† | −6.0 | 0.8 | 21.9 | 19.6 | 107.2 | +$113m |
| Spread: Adj. EBITDA minus GAAP EBIT | +14.9 | +44.9 | +120.2 | +91.8 | +343.7 | $220m SBC |
| GAAP net income to common* | −23.5 | −44.7 | −149.3 | −231.1 | −250.3 | −$699m cum. |
| GAAP basic EPS ($) | −0.41 | −0.49 | −1.31 | −1.16 | −0.91 | 4.8x shares |
| Cash Conversion and Balance Sheet | ||||||
| Operating cash flow (OCF) | −0.9 | 58.7 | 13.8 | −115.4 | 89.7 | +$46m cum. |
| Capital expenditure (capex) | −58.3 | −128.7 | −191.9 | −681.6 | −2,865.8 | −$3.9bn cum. |
| Free cash flow (FCF) | −59.2 | −70.0 | −178.1 | −797.0 | −2,776.1 | −$3.9bn cum. |
| Stock-based compensation (% GAAP rev) | 12.3 (144%) | 32.1 (58%) | 17.4 (11%) | 22.7 (10%) | 220.1 (36%) | 9.7x y/y |
Source: Company SEC Form 10-K filings (FY23-FY26 10-Ks; FY24A-FY26A consolidated)
FY26 GAAP revenue jumped 168% (+274% adjusted) on low-margin fit-out, not recurring rent. Of $611.3m GAAP FY26 revenue, $270.6m (44%) was pass-through Tenant Fit-Out (TFO) construction billed at just ~4.5% margin, while recurring HPC base rent was only $99.8m (16%) and legacy crypto hosting added $154.4m.
Almost no internal cash generation to date: Over five years (FY22A–FY26A), cumulative operating cash flow totaled just +$45.9m against $3,926m of capex, requiring $8.05bn of net external financing. Cash conversion only turns positive in FY29E once $13.2bn of development capex completes.
| Accounting Item | Materiality | How It Flatters Reported / Adjusted Metrics | Penmark Model Treatment |
|---|---|---|---|
| Stock-Based Comp (SBC) | High ($220m) | Excluded from Adjusted EBITDA despite equal to 36% of FY26 GAAP revenue and driving 4.8x share dilution since FY22. | Treated as a real cash-equivalent expense inside our unlevered DCF ($40m–$144m/yr through FY50E). |
| Tenant Fit-Out (TFO) Pass-Through | High ($271m) | Gross construction revenue ($271m FY26A; $330m FY28E) inflates headline revenue growth while contributing only 4.5% margin. | Modeled separately from recurring HPC rent; TFO falls to $0 from FY29E onward. |
| Capitalized Interest | High ($579m) | GAAP capitalizes interest during build ($176m FY27E, $293m FY28E, $110m FY29E), hiding cash interest burden until RFS. | Full cash coupon interest modeled in cash flow; unlevered DCF discounts all cash flows at 8.74% WACC. |
| Macquarie 12.75% PIK Preferred | High ($620m/yr) | Accretes below operating income as redeemable NCI ($295m FY27E → $620m FY30E), keeping Adjusted EBITDA untouched. | Deducted in full from EPS to common and deducted at accreted claim value ($2.01bn+) in equity bridge. |
| Straight-Line Rent and ChronoScale | Medium | ASC 842 straight-lining smooths rent ahead of cash collection; 96%-owned ChronoScale ($72m FY26) consolidated in GAAP. | Core model strips out ChronoScale (valued separately at 50% market) and models lease cash on actual RFS dates. |
We sit 42% above consensus on FY28E revenue but about 50 cents below on EPS
Source: Company filings; Penmark Research estimates
Source: Company filings; Penmark Research estimates
Variable campus costs (~14% of base rent): Property taxes, insurance, site security and maintenance staff scale with energized MW. Power is passed through to hyperscalers at cost under triple-net terms, insulating NOI margins (85%–88% by campus) from electricity price swings.
Corporate G&A and capital costs: Platform cash G&A rises from $70m (FY27E) to $111m (FY30E, 4% of base rent). However, depreciation surges to $1,011m/yr on $19.9bn of capitalized facilities, cash interest reaches $1,086m/yr, and Macquarie PIK hits $620m/yr, keeping common EPS after preferred PIK negative through FY31E.
| Line Item | Penmark | Cons. / Guide | Diff. | Reason for Gap vs Street / Guidance |
|---|---|---|---|---|
| FY27E GAAP Revenue | $1,123m | $958m | +17.3% | We model 350 MW entering service from Dec 2026 to May 2027 (PF2 200 MW by Mar 27, DF1 B1 150 MW in Apr 27) plus $183m of TFO. |
| FY28E GAAP Revenue | $2,653m | $1,870m | +41.9% | Base rent $1,701m ($1,573m signed 1,410 MW + $115m PF2 exp. + $13m Nov lease) + $306m recoveries + $330m TFO + $150m hosting + $166m ChronoScale. |
| FY28E Adj. EBITDA | $1,472m | $1,190m | +23.7% | High 86% incremental NOI margin on faster MW ramp lifts EBITDA $282m ahead of median of three Street data points (Needham, Citizens, MarketScreener). |
| FY27E EPS (after PIK) | −$1.95 | −$1.06 | −$0.89 | We deduct full $295m Macquarie 12.75% PIK and $405m interest expense net of capitalized interest ($273m after $132m interest income); S&P Global consensus expects a smaller loss. |
| FY28E EPS (after PIK) | −$1.25 | −$0.71 | −$0.54 | Despite +$282m higher EBITDA, $444m Macquarie PIK + $683m interest expense keep EPS after PIK deep in red. |
| FY30E (May 2030) vs end-CY30 guide | 1,640 MW | 3.5–4 GW* | −56% | *Management CY30 outlook includes ~2 GW uncontracted pipeline; excluded as 810 MW (plus the 150 MW Nov lease) is unfinanced and power starts 2030+. |
Free cash flow bottoms near −$10bn in FY27E and turns positive in FY29E
Source: Company filings; Penmark Research estimates (no customer prepayments)
Capex profile: Full-year FY27E FCF is −$10.2bn (−$8.2bn for the 9-month stub Sep 2026 to May 2027); remaining dev capex ($13.19bn) runs $8.13bn FY27E, $4.58bn FY28E and $0.48bn FY29E, then drops to ~$56m/yr maintenance capex from FY30E.
Source: Penmark Research estimates (FY27E covers 9-month stub Sep 2026 to May 2027)
Leverage ratio: Net debt + preferred / Adj. EBITDA drops from 29.4x (FY27E) to 12.2x (FY28E), 7.9x (FY29E), and 7.1x (FY31E) after $2.4bn surplus-cash PIK redemption.
We model 80% LTC project debt and Macquarie draws, leaving thin headroom above our $750m minimum cash floor. Funding $13.19bn of remaining development capex across FY27E–FY29E takes $8.68bn of new 7.5% project debt, $1.63bn of Macquarie preferred and $2.88bn of existing cash and operating cash flow (Exhibit 68). Capitalized interest of $579m comes on top. Cash falls $2.72bn to a $957m trough in FY28E.
FY31 refinancing wall: Existing senior notes begin maturing in FY31E ($4.26bn debt repayment modeled against $3.45bn refinancing debt), alongside $2.41bn of cash applied to partially redeem Macquarie’s 12.75% PIK.
TFO billings bridge timing, not economics. Customer deposits are immaterial ($16.8m) and excluded from FCF; TFO billings track fit-out timing, while maintenance capex stays low at ~2% of HPC base rent ($56m/yr at scale) until major refresh capex ($2.6bn) hits during FY41E–FY48E lease expiries.
Common book equity shrinks even as assets nearly double: Because Macquarie’s 12.75% PIK preferred compounds above common equity ($2.01bn → $5.48bn by FY30E), GAAP stockholders’ equity declines from $1.61bn (Aug 2026) to $0.72bn (FY30E) despite $21.8bn in total assets.
| Driver | Sensitivity Tested (Model Setting) | Base DCF | Stressed DCF | Impact / Sh |
|---|---|---|---|---|
| Project Financing and Cost of Capital | WACC −100bp (7.74%) / +100bp (9.74%) | $7.17 | $12.79 / $2.47 | +$5.62 / −$4.70 |
| Lease Origination and Pricing | +300 MW new lease at $2.0m/MW / PF2 unleased | $7.17 | $8.58 / $4.38 | +$1.41 / −$2.79 |
| Lease Escalators (Optionality) | 1.5%/yr variable rent escalator from FY28E | $7.17 | $14.90 | +$7.73 |
| Construction Capex and Delivery | Capex $13.5m/MW / $10.5m/MW on remaining build | $7.17 | $4.08 / $10.69 | −$3.09 / +$3.52 |
| Schedule Execution | Six-month RFS delay on undelivered tranches | $7.17 | $6.10 | −$1.07 |
| Renewal and Residual Value | 50% renewal at 80% rent / 100% at 120% rent | $7.17 | $1.90 / $11.96 | −$5.27 / +$4.79 |
| CoreWeave Counterparty | PF1 rent cut −25% from FY30E (vs 7.5% base) | $7.17 | $5.20 | −$1.97 |
What the Funding Plan Means for Liquidity and Equity Value
Liquidity remains tight through FY28E before turning strongly cash-generative in FY29E. Cash and restricted cash fall from $3.68bn at 31 August 2026 to a $957m trough in FY28E, leaving $207m above our $750m minimum operating float. Any delay in closing the $8.7bn of modeled project debt forces either slower construction or parent-level equity issuance.
Peak senior leverage delays common equity distributions until the early 2030s. Combined debt principal and Macquarie 12.75% PIK preferred peak at $19.9bn in FY30E ($17.2bn net of cash, or 7.4x FY30E Adjusted EBITDA). Free cash flow turns positive at $668m in FY29E and reaches $1.35bn in FY31E, enabling initial preferred redemption and refinancing of FY31 debt maturities.
Our lease DCF gives about $7 a share; the price implies a 7.8% WACC or $9.8m/MW capex
Why lease-by-lease DCF is our primary method: Applied Digital is a leveraged C-corp developer with finite 15–18 year leases, a $13.2bn build wall and $2.6bn of refresh capex, making perpetual REIT multiples misleading. We discount unlevered HPC cash flows from September 2026 through FY50E at an 8.74% weighted average cost of capital (WACC, the blended return required by debt and equity holders). We assume 1.5% terminal growth (the long-run annual cash-flow growth rate after FY50E), add non-HPC assets and cash, and strip senior claims.
| HPC DCF Line ($m) | FY27E* | FY28E | FY29E | FY30E | FY33E | FY43E | FY50E |
|---|---|---|---|---|---|---|---|
| Campus NOI + TFO margin | 403.6 | 1,485.4 | 2,313.7 | 2,391.7 | 2,391.7 | 2,108.9 | 1,913.4 |
| Less: Platform cash G&A | −52.3 | −70.1 | −107.6 | −111.3 | −111.3 | −98.2 | −89.1 |
| Less: Future SBC grants | −40.0 | −75.0 | −77.3 | −79.6 | −86.9 | −116.8 | −143.7 |
| Unlevered HPC EBITDA | 311.2 | 1,340.2 | 2,128.9 | 2,200.9 | 2,193.5 | 1,893.8 | 1,680.6 |
| Less: Cash tax (23% post-NOL) | 0.0 | 0.0 | 0.0 | 0.0 | −275.6 | −206.7 | −157.6 |
| Less: Maint. and refresh capex | −9.2 | −34.0 | −53.8 | −55.7 | −55.7 | −1,132.6 | −44.6 |
| Less: Development capex | −8,132.3 | −4,584.4 | −477.3 | 0.0 | 0.0 | 0.0 | 0.0 |
| Unlevered Free Cash Flow | −7,830.3 | −3,278.2 | 1,597.7 | 2,145.2 | 1,862.2 | 554.6 | 1,478.4 |
| PV at 8.74% WACC (mid-yr) | −7,587.9 | −2,952.2 | 1,323.1 | 1,633.7 | 1,102.8 | 142.1 | 210.6 |
WACC and Roll-Forward
Using APLD’s 1Y regression beta (WACC 11.84%) yields $0.00/sh. Upside risk: our 8.74% WACC relevers the data center REIT asset beta with no debt beta while charging an 8.0% cost of debt. Built consistently, it would be 7.3% to 7.4%, which would put base value above the $12.22 price (the price implies 7.8%). This is the main reason conviction is Low.
Source: Penmark Research estimates
Build cost gives $6.58/sh, 8% below the DCF (within 15%); the gap is the lease development NPV. As of 31 August 2026, APLD had incurred $6,726m of HPC capex at base build cost (against $7,016m GAAP PP&E + prepaids).
Summing $6,726m build cost + $1,025m non-HPC + $3,678m cash − $9,350m of claims (incl. $307m Macquarie 15% common on build cost) = $2,078m equity, divided by 325.8m shares and multiplied by 1.0323 (85-day roll to Nov 24) gives $6.58/sh.
A reverse DCF works backward from the current share price ($12.22) to reveal what single operating or financial input the market is implicitly pricing. Two drivers (capex below guidance and 6.75% terminal growth) look implausible; a 0.99% escalator is possible but unverified; a lower WACC (7.84%) or about 1,120 MW of new leases are plausible paths.
| Single Driver Tested | Penmark Base | Implied @ $12.22 | Gap vs Base | Feasibility Assessment |
|---|---|---|---|---|
| Discount Rate (WACC) | 8.74% | 7.84% | −90 bp | Sits 90 bp below our base WACC (still above the ~6.6% rate implied by the Street’s 19.5x multiple) despite 6.75%–9.25% debt, 12.75% PIK and C-corp tax. |
| Variable Rent Escalator (FY28+) | 0.00% / yr | 0.99% / yr | +99 bp | Not disclosed in 10-Q minimum rent schedule; unverified in filings. |
| Development Capex / MW | $12.00m | $9.77m | −18.6% | Below management’s own $11m–$13m/MW guidance floor. |
| Terminal Growth Rate (Post-FY50) | 1.50% | 6.75% | +525 bp | Implausible: 6.75% growth forever exceeds long-run nominal GDP growth. |
| New Pipeline Leasing (Nov 2026 terms) | 0 MW | +1,120 MW | +1,120 MW | Within management’s 3.5–4.0 GW CY30 outlook, if project debt clears at ~80% LTC. |
A probability-weighted value near $10 rolls to a target near $11 (−7%, Hold)
Source: Penmark Research estimates as of 24 Nov 2026
| Company (Ticker) | Archetype | EV/Rev* | EV/EBITDA* | EBITDA Mgn* | Fully Funded EV/MW |
|---|---|---|---|---|---|
| Applied Digital (at $12.22) | AI-Factory Dev | 3.98x (CY27E) | 5.4x (FY28E) | 59.2% (FY28E) | $12.9m ** |
| Applied Digital (at $11.38 Tgt) | At Penmark Target | 3.84x (CY27E) | 5.3x (FY28E) | 59.2% (FY28E) | $12.8m ** |
| Digital Realty (DLR) | Global DC REIT | 11.46x (CY26E) | 25.6x (TTM) | 47.6% (TTM) | n.a. |
| Equinix (EQIX) | Interconn. REIT | 11.72x (CY26E) | 26.2x (TTM) | 46.2% (TTM) | n.a. |
| Iron Mountain (IRM) | Hybrid DC REIT | 6.75x (TTM) | 19.9x (TTM) | 33.8% (TTM) | n.a. |
| GDS Holdings (GDS) | APAC DC Dev | 3.21x (TTM) | 7.2x (TTM) | 44.9% (TTM) | n.a. |
| CoreWeave (CRWV) | AI Neocloud | 8.99x (TTM) | 17.1x (TTM) | 52.6% (TTM) | n.a. |
| TeraWulf (WULF) | AI-Landlord | 10.11x (CY27E) | n.m. | Neg. (TTM) | n.a. |
| Cipher Digital (CIFR) | AI-Landlord | 9.02x (CY27E) | n.m. | 15.4% (TTM) | n.a. |
| AI-Landlord Median (5 peers) | Primary Peers | 9.02x | n.m. | 8.8%*** | n.a. |
Source: Penmark Research estimates
| Scenario | Prob. | Key Confirmed Stock Driver Assumptions | Today $/sh | 12M Roll* | Rating |
|---|---|---|---|---|---|
| Bear Case | 30% | 6-mo financing/RFS slip; capex $13.5m/MW; NOI −3pp; PF2 unleased; CoreWeave −25% rent; 50%/80% renewal; G&A 5% of rent; 8.5% debt coupon; LTC 70%; ChronoScale 25%. | $0.00 | $0.00 | Sell |
| Base Case | 50% | 1.56 GW on time + 80% PF2 100 MW ($1.92m); capex $12.0m/MW; NOI at guide; 0% escalator; 80%/100% renewal; 7.5% PF1 loss; 8.74% WACC; ChronoScale 50%. | $7.17 | $8.22 | Sell |
| Bull Case | 20% | Capex $11.0m/MW; NOI +2pp; PF2 exp. 100% @ $2.0m; +300 MW pipeline @ $2.0m; +1.5% escalator; 95%/115% renewal; G&A 3.5%; 6.5% debt coupon; ChronoScale 100%. | $31.68 | $36.33 | Buy |
| Weighted | 100% | Expected value rolled 12 months at 14.66% Ke (+$0.00 dividends) → $11.38 Target (−6.9% Total Return vs $12.22) | $9.92 | $11.38 | HOLD |
Six dated milestones over 18 months will test funding, capex and lease escalators
| Timing | Catalyst and Linked Driver | Penmark Expectation | Market / Consensus View | Likely Stock Move |
|---|---|---|---|---|
| ~6 Jan 2027 (Expected) |
Q2 FY27 Results and 10-Q (Construction Capex and Delivery; Lease Origination and Pricing) |
300 MW live in ND; 10-Q confirms zero CPI escalators on Nov 2026 lease; capex ~$12m/MW. | Focus on PF1 NOI margin (~89%) and updated pipeline commentary; date not yet confirmed by company. | ±5–8% if the 10-Q reveals escalators or overruns (pure EPS prints barely move shares: +0.2% to +0.9%). |
| 1Q CY27 (By Mar 27) |
PF2 200 MW RFS and +100 MW Lease (Lease Origination and Pricing; Construction Capex and Delivery) |
200 MW delivered on time; +100 MW leased at ~$1.92m/MW (80% base prob; +$2.79/sh vs 0%). | Bullish Street assumes 100% signing at $2.0m+/MW plus immediate new campus wins. | ±10–15% on signing/rent; −15% if delayed. |
| 1H CY27 (1Q–2Q) |
DF1, PF3 and DF2 Project Debt Close (Project Financing and Cost of Capital) |
80% LTC project debt clears at 7.5% base coupon (~$4.8bn FY27E draw); no common equity. | Market prices 7.0%–7.25% REIT-like debt cost (7.8% implied WACC) with ample lender appetite. | −15–25% if LTC <75% or coupon >8.5%. |
| Apr–Sep 27 | DF1 Initial, PF1 Bldg 3 and PF2 Expansion RFS (Construction Capex and Delivery) |
DF1 150 MW (Apr 27), PF1 final 150 MW (Jul 27) and PF2 expansion 100 MW (Sep 27) push run-rate NOI past $1.1bn. | Management targets $1.0bn NOI run-rate around July 2027; Street expects smooth ramp. | +5–10% if on budget; −15% if substation slips. |
| Jul–Sep 27 | FY27 10-K and DEF 14A Proxy (Project Financing and Cost of Capital) |
FY27 SBC about $160m, falling to $150m in FY28E; Macquarie preferred balance reaches $3.15bn ($235m Sep–May accrual; $295m full-year FY27E); Base Electron note watched closely. | Street largely ignores proxy pay/pledge metrics unless institutional holders push back. | Governance overhang persists unless note repaid. |
| Oct 27– May 28 |
PF3, DF2 and Nov 2026 Lease RFS (Financing and Delivery) |
585 MW energized across PF3 B1 (150), DF1 B2 (150), DF2 (210) and Nov lease A (75); FY28E rev $2.65bn. | Our FY28E revenue ($2.65bn GAAP) sits 42% above consensus ($1.87bn), leaving room for top-line upgrades offset by capital charges. | Revenue beats offset by rising PIK/interest drag. |
| Monitored Indicator | Downside / Sell Triggered If… | Upside / Buy Triggered If… |
|---|---|---|
| Project Debt Pricing and LTC (810 MW unfunded build) |
New project debt clears above 8.5% coupon or below 75% LTC, forcing equity issuance or costly mezzanine capital. | DF1/PF3/DF2 project debt closes at 80%+ LTC and ≤7.25% fixed, allowing Macquarie 12.75% PIK refinancing. |
| Realized Capex / MW (PF2 and DF1 construction) |
Turnkey build cost drifts above $13.0m/MW (−$2.06/sh per +$1m/MW) due to transformer/switchgear inflation. | Standardized design delivers PF2 and DF1 at $10.5m/MW (+$3.52/sh vs Base; about +$2.4/sh at $11.0m/MW). |
| Lease Escalators and Pricing (10-Q rent schedule) |
Filings confirm flat fixed base rent (0% CPI escalator) and PF2’s 100 MW expansion stalls past 1Q CY27. | 10-Q reveals explicit ≥1.5% annual escalators or new 300 MW+ IG leases sign above $2.1m/MW. |
| CoreWeave Credit and Sector (PF1 ~26% rent share) |
CoreWeave debt spreads widen >200 bp or AI-landlord peer multiples remain compressed below 8x EV/Rev. | CoreWeave achieves investment-grade credit metrics or AI-landlord peers re-rate toward 14x+ EV/EBITDA. |
| Governance and SBC Discipline (DEF 14A and 10-Q) |
FY28E SBC expense exceeds our $150m forecast (or recurring new grants exceed $75m/yr), Base Electron draws rise above $59.3m, or CEO share pledges expand. | Board caps SBC <$75m, ties PSUs to ROIC/FCF per share, winds down Base Electron, and unpledges CEO stock. |
Why Hold, Not Sell and What Would Change Our View
Why not Sell: Our bull case ($31.68, 20% weight) supplies $6.34 of the $9.92 weighted value, and rolling that value forward 12 months at the 14.66% cost of equity gives an $11.38 target, 6.9% below $12.22 and inside the Hold band. Bull and bear catalysts roughly cancel out ($3.5/sh vs $3.8/sh). Two operational paths can lift equity above today’s price: signing ~1.1 GW of new leases within management’s 3.5–4.0 GW CY30 outlook, or verifying 1.5% rent escalators.
What moves the call: Base DCF alone ($7.17) already rates Sell (−33% 12-month return), so our Hold rests on the 20% bull weight. A 100bp WACC cut lifts Base to $12.79 (Buy, +20%), while spot weighted value ($9.92) sits 18.8% below $12.22. Financing terms on DF1 and PF3 in 1Q CY27 are our tie-breaker. Holding our $11.38 target fixed, shares below $10.34 rate Buy, $10.34 to $12.64 rate Hold, and above $12.64 rate Sell.
Rent escalators and the discount rate are the biggest upside factors, worth up to about $8 and $6 a share
Risks cut both ways around $12.22, which is why conviction is Low. With 24% of float sold short (66.5m shares), positive surprises on rent escalators or financing costs can trigger sharp short squeezes (+20.3% on 23 Nov 2026), while CoreWeave credit stress (2031 notes ~16%) or capex overruns can quickly reverse gains (−11.6% on 24 Nov 2026).
| Upside Risk to Hold Call | Model Prob. | Value Impact | Mechanism and Why Our Base Case Could Prove Too Conservative |
|---|---|---|---|
| 1. Explicit CPI Rent Escalators | 25% | +$7.73 / sh | Escalator terms are not disclosed in the 10-Q; our Base models 0% annual escalation. If contracts contain 1.5%/yr variable escalators, Base DCF jumps to $14.90/sh. |
| 2. WACC Compression / Rate Cuts | Not modeled | +$5.62 / sh | A −100 bp drop in WACC (8.74% → 7.74%) from lower 10Y Treasury yields or tighter project debt spreads lifts Base DCF to $12.79/sh and flips our rating to Buy (+20% 12m return). |
| 3. Accretive New Leasing and PF2 | 35% / 80% | +$0.70 to +$2.11 | Signing 300 MW of marketed pipeline at $2.0m/MW adds +$1.41/sh, and moving PF2's 100 MW expansion from 80% base probability to 100% adds +$0.70/sh (+$2.11/sh combined). |
| 4. ChronoScale Re-Rating | 30% | +$1.96 / sh | We value APLD’s 96% ChronoScale stake at 50% of market ($618m). If ChronoScale scales toward its $1bn 2027 ARR goal and trades without a holdco discount, equity rises +$1.96/sh. |
| 5. NOI Margins Beat Guide | 40% | +$1.33 / sh | PF1 posted 91% FY26 and 89.4% Q1 FY27 NOI margins vs 88% guide. Sustaining +200 bp above guide across all campuses adds +$1.33/sh in Base DCF. |
| 6. Strategic Takeout / Short Squeeze | Not modeled | +$9–$17 vs Base | Our reference grid at 11–13x FY30E EBITDA (14.66% cost of equity) implies ~$16–$24/sh (+$4–$12 vs price). A hyperscaler or infrastructure fund (e.g., Macquarie buying out APLD’s common interest on funded campuses or parent) could squeeze 66.5m short shares. |
Source: Penmark Research estimates (single-driver upside vs $7.17 base DCF)
Grid Permitting and Utility Regulation
24–48+ month interconnection queues: Campus energization relies on regional utility approvals (MISO/SPP in North Dakota; southern utilities in Louisiana and Alabama) and state transmission siting. Utility delays can trigger liquidated damages or tenant termination rights under the customer leases.
Legal, Completion Guarantees and Litigation
Unquantified completion guarantees: APLD has provided completion guarantees on campus construction projects that are not quantified in filings; cost overruns fall directly on parent equity. Related-party transactions (Base Electron $37m payment and ChronoScale 5.25% management incentive plan units) also carry minority-shareholder litigation risk.
Key-Person and Pledged-Stock Margin Risk
Founder dependence and JPMorgan pledge: Hyperscaler relationships center on CEO Wes Cummins and President Jason Zhang. Cummins has pledged 17.59m shares (75% of his stake, ~5.8% of shares outstanding) to JPMorgan Chase; a further share drop could force involuntary margin selling.
ESG: Power Intensity and Cooling Water
2.2 GW peak grid load scrutiny: Operating 1.6+ GW of critical IT load exposes APLD to state carbon regulations, power-tariff backlash from residential ratepayers, and winter weather reliability standards. Closed-loop liquid cooling mitigates water usage versus evaporative peers.
What Would Decisively Break Our Hold (To Buy or Sell)
Lower financing costs paired with cleaner governance would upgrade our Hold to Buy. Specifically, closing 80% LTC debt below 7.25%, refinancing Macquarie’s 12.75% PIK preferred without dilution, and disclosing recurring 1.5%+ rent escalators would move value toward our $31.68 bull case. Winding down Base Electron loans and capping SBC below $75m/yr would reinforce that shift. Conversely, project debt above 8.5% or a CoreWeave restructuring would tilt our call to Sell.
Crowded bull consensus (17 Buy, 0 Sell) clashes with 24% short interest and a ~90m-share overhang
| Holder (Type) | Shares (m) | % Out. | Value ($m)* |
|---|---|---|---|
| The Vanguard Group (Passive) | 27.59 | 9.13% | $337.2 |
| Hood River Capital Mgmt (Active) | 23.82 | 7.88% | $291.1 |
| Wes Cummins (CEO / Insider)** | 23.36 | 7.73% | $285.5 |
| BlackRock Inc. (Passive) | 15.52 | 5.13% | $189.7 |
| Viking Global Investors (Hedge) | 10.53 | 3.48% | $128.7 |
| Equitec Proprietary Markets (MM) | 8.37 | 2.77% | $102.3 |
| Oasis Management (Hedge) | 6.03 | 1.99% | $73.7 |
| UBS Group AG (Bank / Prime) | 5.54 | 1.83% | $67.7 |
| Value Aligned Research (Active) | 5.27 | 1.74% | $64.4 |
| Geode Capital Management (Passive) | 4.98 | 1.65% | $60.9 |
| State Street Corp. (Passive) | 4.74 | 1.57% | $57.9 |
| Total Reported 13F Institutional (Q3 26) | 193.89 | 64.15% | $2,369.4 |
Street Consensus and Ratings (n=19)
Liquidity, Float and Index Profile
Source: SEC Form 13F (30 Sep 2026) and DEF 14A proxy
Source: FINRA short interest settlement reports to 13 Nov 2026
Crowded short base: Short interest climbed further to 66.5m shares (24.3% of float; 2.3 days to cover, FINRA basis) at the 13 November settlement, creating sharp episodic squeeze risk.
| Instrument | Shares (m) | Strike / Terms |
|---|---|---|
| Basic Shares (incl. Ser. G conv.) | 302.3 | Issued and out. |
| Unvested RSUs, PSUs and RSAs | 15.3 | In base diluted |
| All Warrants (treasury stock method) | 8.3 | 28.1m gross ($7.19–$10.75) |
| Model Base Diluted Shares | 325.8 | Used in DCF |
| Remaining Gross Warrants (above net) | 19.8 | 28.1m − 8.3m net |
| 2.75% Conv. Notes (due 2030) | 46.1 | $450m. We exclude the 2.75% convertible because our value per share if converted ($7.30) is below its $9.76 conversion price, although the notes are in the money at the $12.22 share price. |
| Total Fully Diluted Potential | 391.7m | +30% vs Basic* |
Core statements (ex ChronoScale): $2.3bn FY30E EBITDA offset by about $20bn debt and PIK peak
| Income Statement ($m, except per share) | FY26A | FY27E | FY28E | FY29E | FY30E | FY31E |
|---|---|---|---|---|---|---|
| HPC base rent | 99.8 | 528.2 | 1,700.7 | 2,691.5 | 2,785.1 | 2,785.1 |
| Tenant recoveries and fit-out (TFO) | 285.5 | 278.5 | 636.1 | 484.5 | 501.3 | 501.3 |
| Data center hosting (legacy 286 MW) | 154.4 | 150.0 | 150.0 | 150.0 | 150.0 | 150.0 |
| Adjusted revenue (ex ChronoScale) | 539.7 | 956.7 | 2,486.8 | 3,325.9 | 3,436.4 | 3,436.4 |
| Memo: GAAP revenue (incl. ChronoScale) | 611.3 | 1,122.7 | 2,652.8 | 3,491.9 | 3,602.4 | 3,602.4 |
| Campus NOI + TFO margin + Hosting EBITDA | n.a. | 526.8 | 1,542.4 | 2,370.7 | 2,448.7 | 2,448.7 |
| Platform cash G&A | n.a. | −70.0 | −70.0 | −107.7 | −111.4 | −111.4 |
| Adjusted EBITDA | 107.2 | 456.8 | 1,472.4 | 2,263.1 | 2,337.3 | 2,337.3 |
| Adjusted EBITDA margin (% adj. rev.) | 19.9% | 47.7% | 59.2% | 68.0% | 68.0% | 68.0% |
| Stock-based compensation and D&A | −287.5 | −357.8 | −767.1 | −1,082.1 | −1,106.0 | −1,096.0 |
| Other operating and spin items | −56.2 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
| Operating income (core EBIT) | −236.5 | 99.0 | 705.3 | 1,181.0 | 1,231.3 | 1,241.3 |
| Net interest, tax and other items (incl. Chrono.) | n.a. | −386.8 | −643.6 | −953.9 | −1,025.1 | −935.2 |
| Macquarie PIK and Series E-1 preferred | −65.9 | −300.3 | −449.5 | −551.1 | −625.2 | −704.1 |
| Net income available to common | −249.2 | −588.1 | −387.8 | −324.0 | −418.9 | −397.9 |
| EPS after pref. PIK ($) / Adj. EPS ($) | −0.91 / n.a. | −1.95 / −0.05 | −1.25 / 0.68 | −1.03 / 1.10 | −1.32 / 0.95 | −1.25 / 1.23 |
| Cash Flow Statement ($m) | FY26A* | FY27E (9m) | FY28E | FY29E | FY30E | FY31E |
|---|---|---|---|---|---|---|
| Operating cash flow | 89.7 | 161.0 | 828.8 | 1,309.1 | 1,312.2 | 1,402.2 |
| Development and maintenance capex | −2,865.8 | −8,141.5 | −4,618.4 | −531.2 | −55.7 | −55.7 |
| Capitalized interest (investing) | n.a. | −176.4 | −292.6 | −109.7 | 0.0 | 0.0 |
| Free cash flow (OCF less capex) | −2,776.1 | −8,156.9 | −4,082.3 | 668.2 | 1,256.5 | 1,346.5 |
| New project debt and refinancing draws | n.a.* | 4,807.3 | 3,494.0 | 381.9 | 0.0 | 3,452.4 |
| Macquarie preferred draws / (redemptions) | n.a.* | 901.4 | 655.1 | 71.6 | 0.0 | −2,414.6 |
| Debt repayments and Series E-1 cash divs | −521.5 | −112.9 | −227.1 | −347.0 | −359.9 | −4,262.2 |
| Memo: Net cash from financing activities | 6,876.8 | 5,595.7 | 3,922.1 | 106.4 | −359.9 | −3,224.4 |
| Net change in cash and restricted cash | 4,030.1 | −2,561.2 | −160.2 | 774.7 | 896.7 | −1,877.9 |
| Balance Sheet ($m) and Ratios | 31 Aug 26A | FY27E | FY28E | FY29E | FY30E | FY31E |
|---|---|---|---|---|---|---|
| Cash and restricted cash | 3,677.9 | 1,116.8 | 956.6 | 1,731.3 | 2,627.9 | 750.0 |
| Property and equipment, net | 6,330.4 | 14,477.1 | 18,771.0 | 18,449.8 | 17,494.5 | 16,539.3 |
| Other current and non-current assets | 1,698.8 | 1,698.8 | 1,698.8 | 1,698.8 | 1,698.8 | 1,698.8 |
| Total assets | 11,707.2 | 17,292.7 | 21,426.4 | 21,879.9 | 21,821.3 | 18,988.1 |
| Total debt (net of unamort. costs) | 6,376.6 | 11,075.1 | 14,347.6 | 14,388.1 | 14,033.8 | 13,229.5 |
| AP, accrued, leases and other liabilities | 1,530.3 | 1,530.3 | 1,530.3 | 1,530.3 | 1,530.3 | 1,530.3 |
| Macquarie preferred (accreted NCI) | 2,010.9 | 3,146.8 | 4,245.8 | 4,863.0 | 5,482.6 | 3,766.6 |
| Series E-1 and G preferred | 181.3 | 56.4 | 56.4 | 56.4 | 56.4 | 56.4 |
| Stockholders’ equity (incl. NCI) | 1,608.2 | 1,484.1 | 1,246.3 | 1,042.3 | 718.3 | 405.4 |
| Total debt principal (gross) | 6,721.6 | 11,420.2 | 14,692.7 | 14,733.1 | 14,378.8 | 13,574.5 |
| Net debt + Macq. pref. / Adjusted EBITDA (x)† | n.a. | 29.4x | 12.2x | 7.9x | 7.4x | 7.1x |
| Closing basic shares (m) | 302.3 | 307.3 | 312.4 | 317.5 | 317.5 | 317.5 |
GAAP reconciliations, sector glossary, peer set and model methodology notes
| Reconciliation Line ($m) | FY26A | FY27E | FY28E | FY29E | FY30E |
|---|---|---|---|---|---|
| Adjusted Revenue (Core, ex ChronoScale) | 539.7 | 956.7 | 2,486.8 | 3,325.9 | 3,436.4 |
| Plus: ChronoScale Cloud Revenue (96%-owned spin) | 71.6 | 166.0 | 166.0 | 166.0 | 166.0 |
| GAAP Consolidated Revenue | 611.3 | 1,122.7 | 2,652.8 | 3,491.9 | 3,602.4 |
| Adjusted EBITDA (Company / Core Basis) | 107.2 | 456.8 | 1,472.4 | 2,263.1 | 2,337.3 |
| Less: Stock-Based Compensation (SBC) | −220.1 | −160.0 | −150.0 | −120.0 | −95.0 |
| Less: Depreciation and Amortization (D&A) | −67.4 | −197.8 | −617.1 | −962.1 | −1,011.0 |
| Less: FY26 Other operating and spin items | −56.2 | 0.0 | 0.0 | 0.0 | 0.0 |
| Operating Income (Core / GAAP EBIT) | −236.5 | 99.0 | 705.3 | 1,181.0 | 1,231.3 |
| Adjusted Net Income (Company Basis, ex SBC/PIK) | n.a. | −14.3 | 211.7 | 347.1 | 301.2 |
| Less: SBC, ChronoScale/FV Items, Macquarie PIK and E-1 | n.a. | −573.9 | −599.5 | −671.1 | −720.2 |
| GAAP Net Income Available to Common | −249.2 | −588.1 | −387.8 | −324.0 | −418.9 |
Critical IT Load (MW / GW): Power delivered directly to servers and GPUs, excluding cooling/facility overhead (e.g., 1.56 GW contracted IT load vs 2.2 GW peak utility grid load).
Net Operating Income (NOI): Campus rental revenue minus property-level operating expenses (maintenance, property tax, insurance, site staff), excluding corporate G&A, D&A and interest.
Ready-for-Service (RFS): Contractual milestone when a data center hall passes commissioning and base rent begins accruing.
Tenant Fit-Out (TFO): Pass-through construction services performed by APLD on tenant interiors, billed at ~4.5% margin.
Payment-in-Kind (PIK) Preferred: Macquarie’s 12.75% preferred equity that compounds onto principal rather than paying cash dividends, ranking senior to common stockholders.
Power Usage Effectiveness (PUE): Ratio of total facility power to critical IT power (1.18 target at Polaris Forge via closed-loop liquid cooling vs ~1.4–1.5 legacy average).
Enterprise Value (EV) at Price: Diluted equity at $12.22 ($3,982m, excl. convertible) plus senior secured notes ($6,090m), revolver ($82m), other debt ($99m), leases ($107m), Series E-1 ($62m) and Macquarie preferred ($2,011m), less cash and restricted cash ($3,678m), ChronoScale 96% stake at 50% ($618m) and investments ($122m) = $8,015m. Excludes Macquarie 15% common, capex payables and convertible; does not deduct hosting.
Fully Funded EV / MW: Current EV ($8.02bn) plus remaining FY27–29 development capex ($13.19bn) divided by 1,640 probability-weighted leased MW = $12.93m/MW.
Loan-to-Cost (LTC): Project-level debt financing as a percentage of total turnkey campus build cost (80% Base, 70% Bear).
ROCE: Core Operating Income (EBIT) divided by Net Capital Employed (Net Debt + Preferred Equity + Common Equity).
Peer Set Selection: Two distinct peer cohorts are used because no single public group matches APLD’s profile: (1) Data Center REITs (DLR and EQIX for the 0.810 unlevered asset beta and mature EV/EBITDA; IRM, GDS and NXT.AX shown for global context only); and (2) AI-Landlord and Neocloud Peers (CIFR, WULF, CORZ, HUT, NBIS for CY27E EV/revenue median, plus IREN in the unlevered beta median).
Methodology Note and Model Scope
Business-Model Archetype: Capacity and real-asset developer (hybrid with legacy crypto hosting and 96%-owned ChronoScale cloud). Key performance indicators center on contracted MW, rent per MW-year, NOI margin, development capex per MW and WACC.
Forecast Horizon and Scope: Given the $13.2bn development funding wall and multi-year campus ramp, we project five annual fiscal years (FY27E to FY31E) and value contracted leases through FY50E on a lease-by-lease unlevered DCF basis from the 31 August 2026 balance sheet.
Methodological Notes: Quarterly forecast financial statements are omitted because our model projects annual fiscal periods. Historical 24-month trailing Price-to-Book bands replace five-year forward P/E bands because GAAP EPS remains negative through FY31E. Market prices are as of 24 November 2026 ($12.22), consensus as of 25 November 2026, and publication date is 25 November 2026.
Primary Data Providers and As-Of Dates
Company Disclosures: FY26 Form 10-K (29 July 2026), Q1 FY27 Form 10-Q (7 October 2026), FY26 DEF 14A proxy statement (25 September 2026), Form 8-K filings (October to November 2026), Form 4 insider reports, Form 13F institutional filings (30 September 2026), and company press releases (including the 23 November 2026 150 MW lease).
Earnings Transcripts and Market Data: Q1 FY26 through Q1 FY27 quarterly earnings call transcripts; Databento and Yahoo Finance equity prices through 24 November 2026; S&P Global consensus via Yahoo Finance (revenue and EPS, 25 November 2026) and median of three Street data points (FY28E EBITDA: Needham 8 October 2026, Citizens August 2026, MarketScreener); FINRA short interest (13 November 2026).
Industry Benchmarks: CBRE North America Data Center Trends (2H 2025 and Q1 2026), JLL North America Data Center Report (Midyear 2026), and Congressional Research Service grid-interconnection publications.
Analyst certification and important disclosures
Ratings
Ratings are based on the total return from the share price to our 12-month price target, including dividends. The price target rolls our probability-weighted equity value across bull, base and bear scenarios forward 12 months at the cost of equity.
| Buy | Total return to 12-month target above +10% |
| Hold | Total return to 12-month target from −10% to +10%, inclusive |
| Sell | Total return to 12-month target below −10% |
We review ratings at each set of results and whenever the facts change materially. A share price can move outside its band before the rating changes, and targets may not be reached.
Analyst certification
The Penmark Research Team certifies that (1) the views in this report accurately reflect its views about the subject company and its securities, and (2) no part of its compensation was, is or will be directly or indirectly related to the specific ratings, price targets or views in this report.
Contact
Penmark Research
Questions about our research:
research@penmarkresearch.com
All our research and coverage:
penmarkresearch.com
Basis of preparation
This report uses information publicly available up to its publication date. Share prices are closing prices on the trading day before the publication date, unless stated otherwise. Forecasts, valuations and price targets are Penmark Research’s own, and forecast periods are marked E. Sources are shown beneath each exhibit.
Valuation and price targets
Price targets are based on the valuation methods set out in each report and are weighted across bull, base and bear scenarios. The main risks to each rating and price target are described in the report. Penmark Research updates its coverage after each set of results but is not obliged to update a report at any other time.
Independence and conflicts of interest
Penmark Research is independent. It does not provide investment banking, brokerage, market-making or asset management services, does not trade securities, and does not accept payment from any company for research coverage. Companies do not see or review Penmark Research reports before publication.
No member of the Penmark Research Team holds a long or short position, directly or through derivatives, in the securities of any company Penmark Research covers.
Regulatory status
Penmark Research publishes general, impersonal investment research on a regular basis. It is not registered as an investment adviser with the US Securities and Exchange Commission or any state securities authority, is not a registered broker-dealer and is not a member of FINRA. Penmark Research does not give advice tailored to any person’s circumstances.
Not investment advice or an offer
This report is for information only. It is not personalized investment advice and is not an offer or solicitation to buy or sell any security or other financial instrument. It does not take into account any reader’s objectives, financial situation or needs. Readers should make their own investment decisions and seek independent professional advice where appropriate.
Forward-looking statements and risk
Forecasts, valuations and price targets are estimates based on assumptions that may prove wrong, and they may not be achieved. Opinions are current as of the publication date and may change without notice. Investing in equities involves risk, including the loss of capital. Share prices can be volatile, and past performance is not a reliable indicator of future results.
Data and sources
Company financials, operating data and filings come from company filings, earnings releases and earnings calls. Market data and any consensus estimates come from third-party sources named beneath the relevant exhibit; consensus figures from aggregators are unofficial. Penmark Research does not use other brokers’ research, except published estimates, targets and ratings reported by the third-party sources named beneath each exhibit. Third-party data belong to their providers and may not be extracted from this report.
Accuracy and liability
Information is taken from sources believed to be reliable, but Penmark Research makes no representation or warranty as to its accuracy, completeness or timeliness. To the fullest extent permitted by law, Penmark Research accepts no liability for any loss arising from use of this report. Descriptions of litigation and regulatory matters reflect allegations and public records, not findings, unless stated. If a published report is corrected, the corrected version carries an “Updated” date at penmarkresearch.com.
Distribution and access
Penmark Research reports are available to registered users of penmarkresearch.com. Downloads and programmatic access are governed by the Penmark Research subscription terms. This report is not directed at, or intended for, any person in Singapore or India, and access from those countries is blocked. It is not intended for distribution to, or use by, any person in any jurisdiction where that would be contrary to law or regulation or would subject Penmark Research to registration or licensing requirements there.
Copyright and permitted use
© Penmark Research. All rights reserved. Penmark Research is a trade name of Brightriver Labs. Readers may share a link to this report but may not copy, reproduce, redistribute, sell or use its content, including for text and data mining, without written consent. Contact: research@penmarkresearch.com.